Page 1

Page 2

Page 3

REVISION HISTORY

REV.

DESCRIPTION OF MODIFICATION

DATE

0.

First Issue

9/08/2026

1.

Second Issue

8/09/2026

2.

Third Issue

10/09/2026

3.

Fourth Issue

11/09/2026

CONTENTS

Executive Summary 4

1. Basic Contract Information 7

2. Water Quality 11

3. Waste 19

4. Landfill Gas Monitoring 20

5. Ecology (Coral Monitoring) 24

6. Ecology (Fishery Monitoring) 26

7. Summary of Exceedance, Complaints, Notification of Summons and Prosecutions 29

8. EM&A Site Inspection 31

9. Conclusions and Recommendations 32

Appendix A Overview of Desalination Plant in Tseung Kwan O

Appendix B Summary of Implementation Status of Environmental Mitigation

Appendix C Water Quality Graphical Presentation

Appendix D Site Inspection Proforma

Appendix E Waste Flow Table

Appendix F Summary of Exceedances

Appendix G Complaint Log

Appendix H Event/Action Plan for Noise and Water Quality Monitoring Exceedance

EXECUTIVE SUMMARY

INTRODUCTION

A1. The Project, Design, Build and Operate First Stage of Tseung Kwan O Desalination Plant (TKODP), is a Designated Project under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO) and is currently governed by a Further Environmental Permit (EP No. FEP – 01/503/2015/A and EP No. FEP – 01/503/2015/B) for the construction and operation of the Contract.

A2. In accordance with the Environmental Monitoring and Audit (EM&A) Manual for the Contract, EM&A works for marine water quality, noise, waste management and ecology should be carried out by Environmental Team (ET), Aurecon Hong Kong Limited (Aurecon), during the operation phase of the Contract.

A3. This is the 6th Annual EM&A Review Report, prepared by ASCL, for the Contract summarizing the monitoring results and audit findings of the EM&A programme at and around Tseung Kwan O Area 137 (TKO 137) during the reporting period from 1 May 2025 to 30 April 2026.

A4. The EM&A programme for this contract has covered environmental monitoring and Contractor’s environmental performance auditing in the aspects of dust, noise, water quality, landfill gas, waste management, landscape and visual and ecology.

SUMMARY OF ENVIRONMENTAL MONITORING AND AUDIT WORKS

A5. A summary of the environmental monitoring and audit works undertaken in the reporting period are summarized in Table I.

Table I Summary of Environmental Monitoring Works

Environmental Monitoring works

Frequency

Operation Phase Water Quality Monitoring

130

Operation Phase Coral Monitoring

10

Operation Phase Fishery Monitoring

4

Operation Phase Landfill Gas Monitoring

11

Environmental Site Inspection

52

A6. Operation Phase Impact Water Quality Monitoring was conducted from 1 May 2025 and completed on 30 June 2025. A total of three (3) action level exceedances and eleven (11) limit level exceedances of SS were recorded. Summary of exceedances could be referring to Appendix G.

A7. The continuous monitoring of effluent quality was conducted from 1 May 2025 to 31 July 2025. No exceedance of the sampling was obtained during the reporting period.

A8. According to the approved proposal to change the operation phase EM&A programme for the 2nd to 10th year, continuous monitoring of effluent quality was discontinued and replaced with effluent water monitoring in compliance with discharge license requirements starting from 15 August 2025.

A9. Weekly in-situ monitoring and monthly laboratory measurements of the effluent quality were conducted from September 2025 to April 2026. No exceedance of the results was obtained during the reporting period. The detail results can be referred to the Monthly EM&A Report.

A10. Monthly operational landfill gas monitoring was conducted from 1 May 2025 to 31 July 2025.

A11. According to the approved proposal to change the operation phase EM&A programme for the 2nd to 10th year, landfill gas monitoring will be conducted on a six-month basis starting from August 2025.

A12. A total of five (5) landfill gas monitoring was conducted during the reporting period. No exceedances of the Action or Limit Levels were recorded during the reporting period.

A13. According to the approved proposal to change the operation phase EM&A programme for the 2nd to 10th year, coral monitoring will be conducted on a quarterly basis starting from August 2025.

A14. A total of six (6) operation phase coral monitoring was conducted. There were no AL/LL exceedances observed during the reporting period.

A15. Four (4) operation phase fishery monitoring were conducted during the reporting period. For wet season was carried out in 16 and 23 August 2025 and for dry season was carried out in 7 and 15 February 2026. No AL/LL exceedance was recorded during the reporting period.

COMPLAINT HANDLING AND PROSECUTION

A16. No environmental complaint, notifications of summons and prosecution was received during the reporting period.

REPORTING CHANGE

A17. According to the contractor's information, the Anti-scalant dosage commenced on 10 April 2025. The Anti-scalant water quality test was also conducted starting from the same date.

A18. The works of TKODP were substantially completed on 30 June 2024 and the plant commenced the operation phase on 1 July 2024. A Justification of Termination of the EM&A Programme for the Construction Phase was resubmitted to the EPD on 11 August 2025 and approved by the EPD on 15 August 2025.

A19. A proposal to change the operation phase EM&A programme was submitted to the EPD on 11 August 2025 and approved by the EPD on 15 August 2025.

Page 9

Table 1.1 Contact Details of Key Personnel

Party

Position

Name

Telephone
no.

Remark

Project Proponent
(WSD)

SE/CM2

Milton Law

2634-3573

-

Supervising Officer
(Binnies Hong Kong
Limited)

Project Manager

Augustine Li

2608-7671

-

Senior Resident
Engineer

Mason Pau

6765-4131

-

The Jardine Engineering
Corporation, Limited,
China State Construction
Engineering (Hong
Kong) Limited and
Acciona Agua, S.A.
Trading

Project Manager

Arnes, Parra,
Victor

6468-6710

-

Environmental
Monitoring Manager

Tommy Law

6468-1782

-

Aurecon Hong Kong
Limited

Environmental Team
Leader (ETL)

Toby Wan

9719-5422

-

Lam Environmental
Services Limited

Independent
Environmental Checker
(IEC)

Serena Shek

6149-6683

Until 31 January
2026

SGS Hong Kong Limited

Independent
Environmental Checker
(IEC)

Roy Hung

2774-7406

Started from 1
February 2026

1.4. SUMMARY OF OPERATION WORKS

Detail of the major operation activities undertaken could be referred to Section 1.8 in each monthly EM&A Report.

The status for all environmental aspects is presented in Table 1.2.

Table 1.2 Summary of Status for Key Environmental Aspects under the EM&A Manual

Parameters

Status

Water Quality

Baseline Monitoring under EM&A
Manual

The baseline water quality monitoring was conducted
between 12 May 2020 to 6 June 2020

Construction Phase Marine Impact
Monitoring

Ceased from 1 September 2023

Pre-Operation Phase Marine Impact
Monitoring

Ceased from 30 June 2024

Operation Phase Marine Impact
Monitoring

Completed on 30 June 2025

Parameters

Status

Impact Monitoring of Effluent Discharge
from Main Disinfection

Complete in November 2023 and December 2024

Continuous Monitoring of Effluent
Quality

Ceased from 15 August 2026

Monthly Effluent Quality Monitoring
(Discharge License Requirement)

On-going

Noise

Baseline Monitoring

The baseline noise monitoring result has been
reported in Baseline Monitoring Report and
submitted to EPD under EP Condition 3.4.

Impact Monitoring

Completed

Landfill Gas

Regular Monitoring when construction
works are within the 250 m Consultation
Zone

According to the Contractors, all pits or trenches were
backfilled and undergo reinstatement. No landfill gas
monitoring was carried out. The landfill gas
monitoring was ceased from 31 October 2024.

Monthly Monitoring for buildings,
manholes and utility pits within the
Project Site and along the freshwater
mains

According to the approved proposal to change
the operation phase EM&A programme for the
2 to 10 years, landfill gas monitoring will be
nd th
conducted on a six-month basis starting from
August 2025.

Six-month Basis Monitoring for
buildings, manholes and utility pits
within the Project Site and along the
freshwater mains

On-going

Ecology (Coral)

Pre-operation phase Regular Coral
Monitoring (Monthly)

Completed

Operation phase Regular Coral
Monitoring (Monthly)

According to the approved proposal to change
the operation phase EM&A programme for the
2 to 10 years, coral monitoring will be
nd th
conducted on a quarterly basis starting from
August 2025.

Operation phase Regular Coral
Monitoring (Quarterly)

On-going

Ecology (Fishery)

Pre-operation phase Regular Fishery
Monitoring

Completed

Operation phase Regular Fishery
Monitoring

On-going

Waste Management

Mitigation Measures in Waste
Management Plan

On-going

Ecology (Landscape)

Pre-operation phase Landscape and
Visual Site Inspection

Completed

Operation phase Landscape and Visual
Site Inspection

According to the approved proposal to change
the operation phase EM&A programme for the
2 to 10 years, site inspection will be conducted
nd th
on a bi-weekly basis starting from 15 August
2025.

Environmental Audit

Site Inspection covering Measures of Air
Quality, Noise Impact, Water Quality,
Waste, Ecological Quality, Fisheries,
Landscape and Visual

On-going

Other than the EM&A work by ET, environmental briefings, trainings and regular environmental management meetings were conducted, in order to enhance environmental awareness and closely monitor the environmental performance of the contractors.

The EM&A programme has been implemented in accordance with the recommendations presented in the approved EIA Report and the EM&A Manual. A summary of implementation status of the environmental mitigation measures for the Contract during the reporting period is provided in Appendix B.

2. WATER QUALITY

In accordance with the recommendations of the EIA, water quality EM&A is required during dredging for the submarine pipelines and, during operation phase. In addition, baseline water quality monitoring was prior to the commencement of marine construction activities.

The following Section provides details of the water quality monitoring to be undertaken by the Environmental Team (ET) to verify the distance of sediment and brine plume dispersion and to identify whether the potential exists for any indirect impacts to occur to ecological sensitive receivers.

Water quality monitoring for the Contract can be divided into the following stages:

Dredging activities during construction phase;

⚫

Discharge of effluent from main disinfection during construction phase;

⚫

Pre-operation – before operation phase

⚫

Operation phase – first year upon commissioning; and,

⚫

Continuous monitoring of effluent quality (Operation phase)

⚫

In addition, the marine works contractor is required to complete a silt curtain efficiency test for the combined use of floating silt curtain type and cage type silt curtain for dredging at seawater intake to confirm the silt curtain reduction efficiency assumptions of the assessment. The details of testing plan together with the silt curtain deployment plan shall be submitted by the ET to seek approval from the IEC and EPD.

2.1. WATER QUALITY PARAMETERS

Marine Water Quality Monitoring The parameters that have been selected for measurement in situ and in the laboratory are those that were either determined in the EIA to be those with the most potential to be affected by the construction works or are a standard check on water quality conditions. Parameters to be measured in the impact water quality monitoring are listed in Table 2.1.

Table 2.1 Parameters measured in the impact marine water quality monitoring

Parameters

Unit

Abbreviation

Stage

Operation

In-situ measurements

Dissolved oxygen

mg/L

DO

🗸

Temperature

oC

-

🗸

pH

-

-

🗸

Turbidity

NTU

-

🗸

Salinity

0/00

-

🗸

Total Residual Chlorine

mg/L

TRC

🗸

Parameters

Unit

Abbreviation

Stage

Operation

Laboratory measurements

Suspended Solids

mg/L

SS

🗸

Iron

mg/L

Fe

🗸

In addition to the water quality parameters, other relevant data were measured and recorded in Water Quality Monitoring Logs, including the location of the sampling stations, water depth, time, weather conditions, sea conditions, tidal stage, current direction and velocity, special phenomena and work activities undertaken around the monitoring and works area that may influence the monitoring results.

b) Continuous Monitoring of Effluent Quality

The monitoring requirement for the continuous effluent quality monitoring shall be conducted in accordance with the effluent parameters and standards stipulated by the Water Pollution Control Ordinance Discharge License (No.: WT00044188-2023) conditions. Details derived limit levels for water quality are presented in Table 2.2.

c) Monthly Effluent Monitoring (Water Discharge License)

In accordance with the WT00044188-2023 Part 1, the sampling should be followed the specified frequency, and the parameters of the sample should not be exceeded the limit stated as the water discharge license. Details derived limit levels for water quality are presented in Table 2.2.

Table 2.2 Parameters measured in the Continuous Monitoring of Effluent Quality

Parameters

Unit

Abbreviation

In-situ measurements

Temperature

oC

-

pH

pH

-

Salinity

0/00

-

Total Residual Chlorine

mg/L

TRC

Laboratory measurements

Suspended Solids

mg/L

SS

Iron-Soluble

mg/L

Fe

Total Inorganic Nitrogen

mg/L

-

Total Phosphorus

mg/L

-

Sodium Metabisulphite

mg/L

SMBS

Anti-scalant as Reactive Phosphorus *

mg/L

PO4 as P-

*Remark: Anti-scalant water quality testing will only be conducted whenever anti-scalant dosage is adopted.

Table 2.3 Derived Limit Levels for Water Quality

Parameters

Limit

Monitoring of Effluent Quality

Flow Rate in m3/day

216841

Temperature in °C

Maximum 40

Salinity

71347

SS in mg/L

13

pH

6-9

Iron in mg/L

0.6

Total residual chlorine in mg/L

0.1

Total Inorganic Nitrogen in mg/L

2

Total Phosphorous in mg/L

1

Sodium Metabisulphite in mg/L

0.5

Anti scalant in mg/L*

2.2

*Remark:

1. Anti-scalant water quality testing will only be conducted whenever anti-scalant dosage is adopted.

2.2. MONITORING EQUIPMENT

The monitoring methodology, monitoring equipment and QA/QC procedure could refer to the Monthly EM&A Report.

2.3. MONITORING LOCATION

Marine Water Quality Monitoring The water quality monitoring locations are in accordance with the EM&A Manual and detailed in Table 2.3 and Figure 2.1 below.

Table 2.3 Location of Impact Water Quality Monitoring Station

Station

Easting

Northing

Description

CE

843550

815243

Upstream control station at ebb tide

CF

846843

810193

Upstream control station at flood tide

WSR1

846864

812014

Ecological sensitive receiver at Tung Lung Chau

WSR2

847645

812993

Fisheries sensitive receiver at Tung Lung Chau

WSR3

848023

813262

Ecological sensitive receiver at Tung Lung Chau

WSR4

847886

814154

Ecological sensitive receiver at Tai Miu Wan

WSR16

845039

815287

Ecological sensitive receiver at Fat Tong Chau

Page 16

Page 17

Table 2.4 Derived Action and Limit Levels for Water Quality

Parameters

Action

Limit

Marine Water Quality Monitoring

DO in mg/L

Surface and Middle
7.30 mg L-1
Bottom
7.31 mg L-1
Tung Lung Chau Fish Culture Zone
5.1 mgL-1 or level at control station
(Whichever the lower)

Surface and Middle
4 mg L-1
Bottom
2 mg L-1
Tung Lung Chau Fish Culture Zone
5.0 mgL-1 or level at control station
(Whichever the lower)

SS in mg/L
(Depth-
averaged)

5.00 mg L-1 or 20% exceedance of
value at any impact station
compared with corresponding data
from control station

6.00 mg L-1 or 30% exceedance of value
at any impact station compared with
corresponding data from control
station

Turbidity in
NTU (Depth-
averaged)

2.41 NTU or 20% exceedance of
value at any impact station
compared with corresponding data
from control station

2.84 NTU or 30% exceedance of value
at any impact station compared with
corresponding data from control
station

Salinity in PSU
(Depth-
averaged)

34.25 PSU or 9% exceedance of
value at any impact station
compared with corresponding data
from control station

34.56 PSU or 10% exceedance of value
at any impact station compared with
corresponding data from control
station

Iron in mg/L
(Depth-
averaged)

0.3 mg/L

0.3 mg/L

Total residual
chlorine in mg/L

0.01 mg/L

0.01 mg/L

Total residual
chlorine in mg/L
(Disinfection)

0.1 mg/L

0.1 mg/L

Notes:

i. "Depth-averaged" is calculated by taking the arithmetic means of reading of all three depths.

ii. For DO, non-compliance of the water quality limits occurs when monitoring result is lower than the limits. iii. For Turbidity, SS, iron and Salinity, non-compliance of the water quality limits occurs when monitoring result is higher than the limits.

iv. For the Action and Limit Levels adopted during First-year Operation Phase Monitoring, further review would be made according to the EM&A Manual during Operation Phase.

v. Monitoring of Total Residual Chlorine (Disinfection) will be conducted when cleaning and sterilization of the new freshwater main is carried out.

vi. Monitoring of Iron and Total Residual Chlorine were conducted during the pre-operation phase.

b) Monitoring of Effluent Quality

Table 2.5 Derived Limit Levels for Water Quality

Parameters

Limit

Continuous Monitoring of Effluent Quality

Flow Rate in m3/day

216841

Temperature in °C

Maximum 40

Salinity

71347

SS in mg/L

13

pH

6-9

Iron in mg/L

0.6

Total residual chlorine in mg/L

0.1

Total Inorganic Nitrogen in mg/L

2

Total Phosphorous in mg/L

1

Sodium Metabisulphite in mg/L

0.5

Anti scalant in mg/L*

2.2

*Remark:

1. Anti-scalant water quality testing will only be conducted whenever anti-scalant dosage is adopted.

2.5. MONITORING PROGRAMME

Marine Water Quality Monitoring The ET of the Contract conducted the operation phase marine water quality monitoring between 1 May 2025 and 30 June 2025 at the thirteen designated monitoring stations near TKO in accordance with the EM&A Manual and Contract Specification.

2.6. MONITORING RESULTS AND OBSERVATIONS

Operation Phase The first-year operation phase marine water quality monitoring was carried out during the reporting period, the monitoring was conducted at the thirteen monitoring stations (CE, CF, WSR1, WSR2, WSR3, WSR4, WSR16, WSR33, WSR36, WSR37, NF1, NF2 and NF3). The Action and Limit Level would be referred to the approved EM&A Manual Table 5.4 Firstyear Operation Phase Marine Water Monitoring.

The water quality monitoring at the designated locations were conducted by the ET as scheduled in the reporting period. The graphical presentation of the water quality monitoring result was shown in Appendix C.

A total of three (3) action level exceedances and eleven (11) limit level exceedances of SS were recorded. Summary of exceedances could be referring to Appendix F.

Continuous Monitoring of Effluent Quality The continuous monitoring of effluent quality was conducted from 1 May 2025 to 31 July 2025. No exceedance of the sampling was obtained during the reporting period.

Monthly Effluent Monitoring (Water Discharge License) According to the approved proposal to change the operation phase EM&A programme for the 2nd to 10th year, continuous monitoring of effluent quality was discontinued and replaced with effluent water monitoring in compliance with discharge license requirements starting from 15 August 2025.

Weekly in-situ monitoring and monthly laboratory measurements of the effluent quality were conducted from September 2025 to April 2026. No exceedance of the results was obtained during the reporting period. The detailed results can be referred to the Monthly EM&A Report.

3. WASTE

The waste generated from this Project includes inert construction and demolition (C&D) materials, and non-inert C&D materials. Non-inert C&D materials are made up of general refuse, vegetative wastes and recyclable wastes such as plastics and paper/cardboard packaging waste. Steel materials generated from the project are also grouped into non-inert C&D materials as the materials were not disposed of with other inert C&D materials. Details of cumulative waste management data are presented as a waste flow table in Appendix E.

4. LANDFILL GAS MONITORING

4.1. MONITORING REQUIREMENT

In accordance with Section 11 of the EM&A Manual, monthly monitoring of landfill gas is required for the first year of operation at buildings within the Project Site and consultation zone. Part of the desalination plant and the indicative area of natural slope mitigation works fall within the SENT Landfill Extension Consultation Zone; and part of the 1,200 mm diameter freshwater mains along Wan Po Road falls within the SENT Landfill and SENT Landfill Extension Consultation Zones, TKO Stage II/III Restored Landfill and TKO Stage I Restored Landfill Consultation Zones.

Routine monitoring is required at buildings within the Project Site and consultation zones. The monitoring frequency will be monthly for the first year of operation.

For the manholes and utility pits within the Project Site and along the fresh water mains, each manhole/ utility pit should be monitored with two measurements (at mid depth and base). Each measurement should be monitored for a minimum of 10 minutes. A steady reading and peak reading should be recorded at each manhole/ utility pit and for each measurement.

Monitoring oxygen, methane, carbon dioxide and barometric pressure would be performed monthly during the operation phase.

The area required to be monitored for landfill gas in the reporting period is shown in Figure 4.1, Figure 4.2 and Figure 4.3.

Page 23

Page 24

4.4. MONITORING RESULTS AND OBSERVATIONS

Five (5) times of landfill gas monitoring were conducted in the reporting period. No action or limit level exceedance was recorded in the reporting period.

Action and Limit Level are provided in Table 4.1.

Table 4.1 Action / Limit Levels and Event and Action Plan for LFG Hazard

Parameters

Action Level

Limit Level

Oxygen (O )
2

<19% O
2

<19% O
2

Methane (CH )
4

>10% LEL

>20% LEL

Carbon Dioxide (CO )
2

>0.5% CO
2

>1.5% CO
2

Page 26

Table 5.1 Action and Limit Level for Coral Monitoring Equipment

Parameter

Action Level Definition

Limit Level Definition

Mortality

If during Impact Monitoring a
15% increase in the percentage
of partial mortality on the corals
occurs at more than 20% of the
tagged indirect impact site coral
colonies that is not recorded on
the tagged corals at the control
site, then the Action Level is
exceeded

If during Impact Monitoring a
25% increase in the percentage
of partial mortality on the corals
occurs at more than 20% of the
tagged indirect impact site coral
colonies that is not recorded on
the tagged corals at the control
site, then the Limit Level is
exceeded

Note: If the defined Action Level or Limit Level for coral monitoring is exceeded, the actions as set out in Table E3 of Appendix E will be implemented.

If non-compliance were found during the construction works, the actions in accordance with the Event and Action Plan will be carried out according to Appendix H.

MONITORING FREQUENCY Operation phase coral monitoring shall be monitored once per month as the requirement of the first year of operational phase.

According to the approved proposal to change the operation phase EM&A programme for the 2nd to 10th year, coral monitoring will be conducted on a quarterly basis starting from August 2025.

MONITORING RESULT AND OBSERVATION

A total of eight (8) operation phase coral monitoring were conducted. There were no AL/LL exceedances observed during the reporting period. The detailed result of the monitoring is presented in Appendix I of the Monthly EM&A Report.

6. ECOLOGY (FISHERY MONITORING)

The purpose of the operation phase regular fisheries monitoring programme is to monitor the potential impacts on fisheries resources in the vicinity of the project site. Apart from the regular fisheries monitoring programme, a water quality monitoring programme in addition to the water quality monitoring programme in the approved EM&A Manual is also described in Section 2.4 to (i) provide supplementary information in the interpretation of the findings of the fisheries monitoring and (ii) assist the monitoring of the potential impact on the Tung Lung Chau Fish Culture Zone (FCZ) in Joss House Bay.

MONITORING LOCATION In accordance with Section 2.3 of the approved Methodology Paper on Regular Fisheries Monitoring, it is recommended to set up six (6) fisheries monitoring locations in Joss House Bay and its vicinity to monitor the fisheries resources.

Two (2) sampling locations are set up in close proximity of the direct footprint of the proposed submarine utilities around TKO Area 137. These sampling locations represent the potential Project impact zones (i.e. areas at and in close proximity to the footprint of the proposed submarine utilities that will be directly affected by the Project works).

Two (2) gradient locations are proposed between the proposed submarine utilities and Tung Lung Chau FCZ to assist in the interpretation and identification of any potential fisheries impact in the vicinity of the FCZ.

Two (2) reference locations are proposed in the outer Joss House Bay between the waters of Tung Lung Chau and Fat Tong Mun. These reference locations are further away and will not be affected by the Project discharge (based on the EIA prediction) and will serve as control stations. Any significant fisheries impact identified at the reference locations should be caused by other natural factors or non-Project activities. The trends of fisheries conditions recorded in the reference locations will be used to assist in the interpretation of the trends of fisheries impact identified in the impact and gradient locations.

The coordinates of the proposed monitoring locations are shown in Figure 7.1.

Page 29

MONITORING RESULT AND OBSERVATION Four (4) operation phase fishery monitoring were conducted during the reporting period. For wet season was carried out in 16 and 23 August 2025 and for dry season was carried out in 7 and 15 February 2026. No AL/LL exceedance was recorded during the reporting period. The detailed result of the monitoring is presented in the Monthly EM&A Report.

Page 31

Operation Phase Impact Water Quality Monitoring was conducted from 1 May 2025 and completed on 30 June 2025. A total of three (3) action level exceedances and eleven (11) limit level exceedances of SS were recorded.

The continuous monitoring of effluent quality was conducted from 1 May 2025 to 31 July 2025. No exceedance of the sampling was obtained during the reporting period.

According to the approved proposal to change the operation phase EM&A programme for the 2nd to 10th year, continuous monitoring of effluent quality was discontinued and replaced with effluent water monitoring in compliance with discharge license requirements starting from 15 August 2025.

Weekly in-situ monitoring and monthly laboratory measurements of the effluent quality were conducted from September 2025 to April 2026. No exceedance of the results was obtained during the reporting period. The detail results can be referred to the Monthly EM&A Report.

Monthly operational landfill gas monitoring was conducted from 1 May 2025 to 31 July 2025.

According to the approved proposal to change the operation phase EM&A programme for the 2nd to 10th year, landfill gas monitoring will be conducted on a six-month basis starting from August 2025.

A total of five (5) landfill gas monitoring was conducted during the reporting period. No exceedances of the Action or Limit Levels were recorded during the reporting period.

According to the approved proposal to change the operation phase EM&A programme for the 2nd to 10th year, coral monitoring will be conducted on a quarterly basis starting from August 2025.

A total of eight (8) operation phase coral monitoring was conducted. There were no AL/LL exceedances observed during the reporting period.

Four (4) operation phase fishery monitoring were conducted during the reporting period. For wet season was carried out in 16 and 23 August 2025 and for dry season was carried out in 7 and 15 February 2026. No AL/LL exceedance was recorded during the reporting period.

No complaint, notification of summons and prosecution was received in the reporting period. Summary of complaint log are presented in Appendix G.

8. EM&A SITE INSPECTION

Site inspections were carried out on a weekly basis to monitor the implementation of proper environmental pollution control and mitigation measures under the Contract from May 2025 to August 2025.

According to the approved proposal to change the operation phase EM&A programme for the 2nd to 10th year, site inspection will be conducted on a bi-weekly basis starting from 15 August 2025.

Thirty-seven (37) site inspections were carried out in the reporting period.

Environmental deficiencies were observed during weekly site inspection. Key observations during the site inspections and during the reporting period could be referring to Appendix D and corresponding Monthly Report.

According to the EIA Study Report, Environmental Permit, contract documents and EM&A Manual, the mitigation measures detailed in the documents should be implemented as much as practical during the reporting period. An updated Implementation Status of Environmental Mitigation Measures (EMIS) is provided in Appendix B.

9. CONCLUSIONS AND RECOMMENDATIONS

This is the 6th Annual EM&A Review Report for the Project which summarizes the key findings of the EM&A programme during the reporting period from 1 May 2025 to 30 April 2026, in accordance with the EM&A Manual and the requirement under FEP – 01/503/2015/A and FEP – 01/503/2015/B.

Operation Phase Impact Water Quality Monitoring was conducted from 1 May 2025 and completed on 30 June 2025. A total of three (3) action level exceedances and eleven (11) limit level exceedances of SS were recorded.

The continuous monitoring of effluent quality was conducted from 1 May 2025 to 31 July 2025. No exceedance of the sampling was obtained during the reporting period.

According to the approved proposal to change the operation phase EM&A programme for the 2nd to 10th year, continuous monitoring of effluent quality was discontinued and replaced with effluent water monitoring in compliance with discharge license requirements starting from 15 August 2025.

Weekly in-situ monitoring and monthly laboratory measurements of the effluent quality were conducted from September 2025 to April 2026. No exceedance of the results was obtained during the reporting period. The detail results can be referred to the Monthly EM&A Report.

Monthly operational landfill gas monitoring was conducted from 1 May 2025 to 31 July 2025.

According to the approved proposal to change the operation phase EM&A programme for the 2nd to 10th year, landfill gas monitoring will be conducted on a six-month basis starting from August 2025.

A total of five (5) landfill gas monitoring was conducted during the reporting period. No exceedances of the Action or Limit Levels were recorded during the reporting period.

According to the approved proposal to change the operation phase EM&A programme for the 2nd to 10th year, coral monitoring will be conducted on a quarterly basis starting from August 2025.

A total of six (6) operation phase coral monitoring was conducted. There were no AL/LL exceedances observed during the reporting period.

Four (4) operation phase fishery monitoring were conducted during the reporting period. For wet season was carried out in 16 and 23 August 2025 and for dry season was carried out in 7 and 15 February 2026. No AL/LL exceedance was recorded during the reporting period.

Environmental site inspection was conducted during the reporting period. Minor deficiency was observed during site inspection. The environmental performance of the project was therefore considered satisfactory.

According to the environmental site inspections performed in the reporting period, the Contractor is reminded to pay attention on maintaining proper materials storage, site tidiness and chemical storage on site.

No environmental complaint, notifications of summons and prosecution was received during the reporting period.

The ET will keep track on the construction works to confirm compliance of environmental requirements and the proper implementation of all necessary mitigation measures.

Appendix A

Overview of Desalination Plant in Tseung Kwan O

Page 37

Page 38

Appendix B

Summary of Implementation Status of Environmental Mitigation

EIA
Reference

Recommended Environmental Protection Measures/
Mitigation Measures

Objectives of the
recommended measures &
main concerns to address

Implementation Agent

Implementation
Stage

Implementation
status

Relevant Legislation
& Guidelines

D

C

O

Air Quality

S4.8.1

Ultra-low-sulphur diesel (ULSD) will be used for all construction
plant on-site, as defined as diesel fuel containing not more than
0.005% sulphur by weight) as stipulated in Environment,
Transport and Works Bureau Technical Circular (ETWB-TC(W))
No 19/2005 on Environmental Management on Construction Sites.

Land site/ During
construction/ During
Operation

Contractor(s)

✓

✓

Implemented

Environment, Transport
and Works Bureau
Technical Circular
(ETWB- TC(W)) No
19/2005 on
Environmental
Management on
Construction Sites

Water Quality

S6.9 and
S6.12

The sterilization water should be dechlorinated with total residual
chlorine (TRC) level below 1 mg/L before discharge to public
sewer. In situ testing of TRC should also be conducted for the
discharge of chlorinated water for pipeline disinfection to ensure
sufficient dechlorination before discharge to public sewer.

Sterilization of water mains
prior to commissioning

Contractor(s)

✓

✓

Implemented

Technical
Memorandum for
Effluents Discharged
into Drainage and
Sewerage Systems
Inland and Coastal
Waters

S6.9

The cleaning and flushing water should also be treated and desilted
to the relevant discharge requirement stipulated in TM-DSS before
discharging.

Sterilization of water mains
prior to commissioning

Contractor(s)

✓

✓

Implemented

S6.9

Site drainage should be well maintained, and good construction
practices should be observed to ensure that oil, fuels, solvents, and
other chemicals are managed, stored and handled properly and do
not enter the nearby water streams.

Land site & drainage/ During
construction/ During
operation

Contractor(s)

✓

✓

Implemented

-

Waste Management

S8.5

Provision of sufficient waste disposal points and regular collection
for disposal.

All area/ During construction/
During operation

Contractor(s)

✓

✓

Implemented

DEVB TC(W) No.
8/2010, Enhanced
Specification for Site
Cleanliness and
Tidiness.

S8.5

Chemical waste container shall be suitable for the substance they
are holding, resistant to corrosion, maintained in a good condition,
and securely closed.

All area/ During
construction/ During
operation

Contractor(s)/ WSD

✓

✓

Implemented

Waste Disposal
(Chemical Waste)
(General) Regulation;
Code of Practice on
the Packaging,
Handling and Storage
of Chemical Wastes

S8.5

Chemical waste container shall have a capacity of less than 450 L
unless the specifications have been approved by the EPD.

All area/ During
construction/ During
operation

Contractor(s)/ WSD

✓

✓

Implemented

S8.5

A label in English and Chinese shall be displayed on the chemical
container in accordance with instructions prescribed in Schedule 2
of the Regulations.

All area/ During
construction/ During
operation

Contractor(s)/ WSD

✓

✓

Implemented

EIA
Reference

Recommended Environmental Protection Measures/
Mitigation Measures

Objectives of the
recommended measures &
main concerns to address

Implementation Agent

Implementation
Stage

Implementation
status

Relevant Legislation
& Guidelines

D

C

O

S8.5

Storage areas for chemical waste shall be enclosed on at least 3
sides.

All area/ During
construction/ During
operation

Contractor(s)/ WSD

✓

✓

Implemented

S8.5

Storage areas for chemical waste shall have an impermeable floor
and bunding, of capacity to accommodate 110% of the volume of
the largest container or 20% by volume of the chemical waste
stored in that area, whichever is the greatest.

All area/ During
construction/ During
operation

Contractor(s)/ WSD

✓

✓

Implemented

S8.5

Storage areas for chemical waste shall have adequate ventilation.

All area/ During
construction/ During
operation

Contractor(s)/ WSD

✓

✓

Implemented

S8.5

Storage areas for chemical waste shall be covered to prevent
rainfall entering (water collected within the bund must be tested
and disposed of as chemical waste, if necessary).

All area/ During
construction/ During
operation

Contractor(s)/ WSD

✓

✓

Implemented

S8.5

Storage areas for chemical waste shall be arranged so that
incompatible materials are appropriately separated.

All area/ During
construction/ During
operation

Contractor(s)/ WSD

✓

✓

Implemented

S8.5

General refuse will be stored in enclosed bins or compaction units
separately from construction and chemical wastes.

All area/ During
construction/ During
operation

Contractor(s)/ WSD

✓

✓

Implemented
after reminder

S8.5

Adequate number of waste containers will be provided to avoid
over-spillage of waste.

All area/ During
construction/ During
operation

Contractor(s)/ WSD

✓

✓

Implemented

DEVB TC(W) No.
8/2010
Enhanced
Specification for Site
Cleanliness and
Tidiness.

S8.5

A reputable waste collector will be employed by the Contractor to
remove general refuse from the site, separately from construction
and chemical wastes, on a daily basis to minimize odour, pest and
litter impacts.

All area/ During
construction/ During
operation

Contractor(s)/ WSD

✓

✓

Implemented

-

S8.5

Recycling bins will be provided at strategic locations within the Site
to facilitate recovery of recyclable materials (including aluminum
can, wastepaper, glass bottles and plastic bottles) from the Site.
Materials recovered will be sold for recycling.

All area/ During
construction/ During
operation

Contractor(s)/ WSD

✓

✓

Implemented

-

Landscape & Visual

S11.10 &
11.11

The construction area and area allowed for temporary structures,
such as the contractor’s office, will be minimized to a practical
minimum. (MM1)

All area/ Detailed design/
During construction/ During
operation

WSD/ Contractor(s)

✓

✓

✓

Implemented

-

EIA
Reference

Recommended Environmental Protection Measures/
Mitigation Measures

Objectives of the
recommended measures &
main concerns to address

Implementation Agent

Implementation
Stage

Implementation
status

Relevant Legislation
& Guidelines

D

C

O

S11.10 &
11.11

At the detailed design stage, the design team will seek to minimize
the landscape footprint of the Project and above ground facilities,
while satisfying all other requirements. (MM2)

All area/ Detailed design/
During construction/ During
operation

WSD/ Contractor(s)

✓

✓

✓

Implemented

-

S11.10 &
11.11

Design principles will be adopted to take into account the
surrounding area, particularly Clear Water Bay Country Park
behind and the nearby waterfront, with due consideration given
to:
- green roofs where practical (i.e. without equipment on the roof);
- roadside planting;
- aesthetic treatment of all structures;
- vertical greening;
- screen planting along application site; and
- landscape enhancement with amenity planting where practical
including planting along the edge (site boundary) fence with
native shrubs where feasible, to reduce their visual impact and
blend them into the surrounding landscape. (MM3)

All area/ Detailed design/
During construction/ During
operation

WSD/ Contractor(s)

✓

✓

✓

Implemented

-

S11.10 &
11.11

All trees within the Project Site or the potential slope mitigation
works area will be carefully protected during construction
according to DEVB TCW No. 10/2013 – Tree Preservation (MM4)

All area/ Detailed design/
During construction/ During
operation

WSD/ Contractor(s)

✓

✓

✓

Implemented

ETWB TCW No. 3/2006
- Tree Preservation.

S11.10 &
11.11

No tree within the Country Park will be felled. Trees within the
Site unavoidably affected by the works will be transplanted where
necessary and practical. For trees that need to be felled,
compensatory planting will be provided to the satisfaction of
relevant Government departments.
A compensatory tree planting proposal including locations of tree
compensation will be submitted to seek relevant government
department’s approval, in accordance with DEVB TC(W) No.
10/2013. (MM5)

All area/ Detailed design/
During construction/ During
operation

WSD/ Contractor(s)

✓

✓

✓

Implemented

DEVB TC(W) No.
10/2013

S11.10 &
11.11

Any slope mitigation works necessary to address natural terrain
hazards, will be minimized to minimize any potential
environmental impact to the Country Park e.g. soil nailing and rock
stabilization will aim to avoid existing trees e.g. should any
restoration of vegetation be necessary, the best planting matrix
with native species will be established, with the aim of resembling
the existing vegetation. (MM6)

All area/ Detailed design/
During construction/ During
operation

WSD/ Contractor(s)

✓

✓

✓

Implemented

S11.10 &
11.11

Dredging works for the installation of intake structures and outfall
diffusers should be minimized to avoid or reduce any potential
environmental impacts to as low as reasonably practicable
(ALARP). The intake and outfall structures (e.g. intake openings and
diffuser heads) will be prefabricated and transferred to site for

All area/ Detailed design/
During construction/ During
operation

WSD/ Contractor(s)

✓

✓

✓

Implemented

EIA
Reference

Recommended Environmental Protection Measures/
Mitigation Measures

Objectives of the
recommended measures &
main concerns to address

Implementation Agent

Implementation
Stage

Implementation
status

Relevant Legislation
& Guidelines

D

C

O

installation. (MM7)

S11.10 &
11.11

All night-time lighting will be reduced to a practical minimum
both in terms of number of level and will be hooded and
directional. (MM8) units and lux level and will be hooded and
directional. (MM8)

All area/ Detailed design/
During construction/ During
operation

WSD/ Contractor(s)

✓

✓

✓

Implemented

-

Landfill Gas Hazard

S12.7

During all works, safety procedures should be implemented to
minimize the risks of fires and explosions, asphyxiation of workers
and toxicity effects resulting from contact with contaminated soil
and groundwater.

All area/ Detailed design/
During construction/operation

Contractor(s)

✓

✓

✓

Implemented

-

S12.7

During trenching and excavation as well as creation of confined
spaces at near to or below ground level, precautions should be
clearly laid down and rigidly Gas detection equipment and
appropriate breathing apparatus should be available and used
when entering confined spaces or trenches deeper than 1 meter.

All area/ Detailed design/
During construction/operation

Contractor(s)

✓

✓

✓

Implemented

S12.7

The Contractor should make the workers are aware of potential
hazards of working in confined spaces (any chamber, manhole or
culvert which is large enough to permit access to personnel). Such
work in confined spaces is controlled by the Factories and
Industrial Undertakings (Confined Spaces) Regulations of the
Factories and Industrial Undertakings Ordinance.
Following the Safety Guide to Working in Confined Spaces ensures
compliance with the above regulations.

All area/ Detailed design/
During construction/operation

Contractor(s)

✓

✓

✓

Implemented

S12.7

Safety officers, specifically trained with regard to landfill gas and
leachate related hazards and the appropriate actions to take in
adverse circumstances, should be present on the site throughout
the works, in particular, when works are undertaken below grade.

All area/ Detailed design/
During construction/operation

Contractor(s)

✓

✓

✓

Implemented

S12.7

All personnel who work on site and all visitors to the site should be
made aware of the possibility of ignition of gas in the vicinity of the
works, the possible presence of contaminated water and the need
to avoid physical contact with it.

All area/ Detailed design/
During construction/operation

Contractor(s)

✓

✓

✓

Implemented

S12.7

Monitoring for landfill gas should be undertaken in all excavations,
manholes, chambers (particularly during pipe jacking) and any
confined spaces through the use of an intrinsically safe portable
instrument, appropriately calibrated and capable of measuring the
concentrations of methane. carbon dioxide and oxygen.

All area/ Detailed design/
During construction/operation

Contractor(s)

✓

✓

✓

Implemented

S12.7

Monitoring frequency and areas to be monitored should be
specified prior to commencement of groundwork, either by the
Safety Officer, or by an appropriately qualified person. All
measurements should be recorded and documented.

All area/ Detailed design/
During construction/operation

Contractor(s)

✓

✓

✓

Implemented

EIA
Reference

Recommended Environmental Protection Measures/
Mitigation Measures

Objectives of the
recommended measures &
main concerns to address

Implementation Agent

Implementation
Stage

Implementation
status

Relevant Legislation
& Guidelines

D

C

O

S12.7

Proceed drilling with adequate care and precautions against the
potential hazards which may be encountered.

All area/ Detailed design/
During construction/operation

Contractor(s)

✓

✓

✓

Implemented

S12.7

Prior to the commencement of the site works, the drilling
contractor should devise a 'method-of- working' statement
covering all normal and emergency procedures (including but not
limited to number of operatives, experience and special skills of
operatives, normal method of operations, emergency procedures,
supervisors responsibilities, storage and use of safety equipment,
safety procedures and signs, barriers and guarding). The site
supervisor and all operatives must be familiar with this statement.

All area/ During
construction/operation

Contractor(s)

✓

✓

✓

Implemented

S12.7

Where below ground service entries are necessary to the Incoming
Switchgear Room, 132 kV Substation and Chlorine Store (I) and
(II), the entry point should be sealed to prevent gas entry. In
addition, any below grade cable trenches entering the Incoming
Switchgear Room and 132 kV Substation can become the pathway
for landfill gas and hence grilled metal covers should be used.

All area/ Detailed design/
During construction/operation

Contractor(s)

✓

✓

✓

Implemented

S12.7

It is recommended regular landfill gas monitoring should be
carried out at the Incoming Switchgear Room, 132 kV Substation
and Chlorine Store (I) and (II). The monitoring frequency will be
monthly for the first year of operation. If the monitoring results
show no sign of landfill gas migration, reduce the monitoring
frequency to once every six months.

All area/ Detailed design/
During construction/operation

Contractor(s)

✓

✓

✓

Implemented

S12.7

The manholes and utility pits within the Project Site and along the
fresh water mains. Each manhole/ utility pit should be monitored
with two measurements (at mid depth and base). Each
measurement should be monitored for a minimum of 10 minutes.
A steady reading and peak reading should be recorded at each
manhole/ utility pit and for each measurement. The need for
venting the manhole/ utility pit and further monitoring will be
reviewed after the initial monitoring.

All area/ Detailed design/
During construction/operation

Contractor(s)

✓

✓

✓

Implemented

S12.7

All construction, operation and maintenance personnel working
on-site as well as visitors should be made aware of the hazards of
landfill gas and its possible presence on-site. This should be
achieved through a combination of posting warning signs in
prominent places and also by access to detailed information on
landfill gas hazards and the designs and procedural means by
which these hazards are being minimized on-site.

All area/ Detailed design/
During construction/operation

Contractor(s)

✓

✓

✓

Implemented

Note: D – Design stage C – Construction O – Operation

Appendix C

Water Quality Monitoring Graphical Presentation

 Appendix C.1 Weather Condition

 Appendix C.2 Other Factor Might Affect the Monitoring Results

Page 46

Page 47

Page 48

Page 49

Page 50

Page 51

Page 52

Page 53

Page 54

Page 55

Page 56

Page 57

Page 58

Page 59

Page 60

Page 61

Page 62

Page 63

Page 64

Page 65

Page 66

Page 67

Appendix C.1

Weather Condition

Page 69

Page 70

Appendix C.2 Other Factor Might Affect the Monitoring Results

Other Factors might affect the monitoring results

Reporting Period

May 2025

Jun 2025

N/A

N/A

Appendix D

Site Inspection Proforma

Table E1 Site Inspection Observation Record

Date

Environmental Observations

Follow-up Status

May 2025

7 May 2025

No major environmental deficiency was
observed.

N/A

13 May 2025

No major environmental deficiency was
observed.

N/A

20 May 2025

No major environmental deficiency was
observed.

N/A

30 May 2025

No major environmental deficiency was
observed.

N/A

June 2025

3 Jun 2025

No major environmental deficiency was
observed.

N/A

10 Jun 2025

No major environmental deficiency was
observed.

N/A

17 Jun 2025

No major environmental deficiency was
observed.

N/A

23 Jun 2025

No major environmental deficiency was
observed.

N/A

July 2025

3 Jul 2025

No major environmental deficiency was
observed.

N/A

10 Jul 2025

No major environmental deficiency was
observed.

N/A

17 Jul 2025

No major environmental deficiency was
observed.

N/A

24 Jul 2025

No major environmental deficiency was
observed.

N/A

31 Jul 2025

No major environmental deficiency was
observed.

N/A

Date

Environmental Observations

Follow-up Status

August 2025

7 Aug 2025

No major environmental deficiency was
observed.

N/A

14 Aug 2025

No major environmental deficiency was
observed.

N/A

28 Aug 2025

No major environmental deficiency was
observed.

N/A

September 2025

10 Sept 2025

No major environmental deficiency was
observed.

N/A

25Sept 2025

No major environmental deficiency was
observed.

N/A

October 2025

9 Oct 2025

No major environmental deficiency was
observed.

N/A

23 Oct 2025

No major environmental deficiency was
observed.

N/A

November 2025

3 Nov 2025

No major environmental deficiency was
observed.

N/A

20 Nov 2025

No major environmental deficiency was
observed.

N/A

25 Nov 2025

No major environmental deficiency was
observed.

N/A

December 2025

11 Dec 2025

No major environmental deficiency was
observed.

N/A

22 Dec 2025

No major environmental deficiency was
observed.

N/A

January 2026

9 Jan 2026

No major environmental deficiency was
observed.

N/A

21 Jan 2026

No major environmental deficiency was
observed.

N/A

February 2026

3 Feb 2026

No major environmental deficiency was
observed.

N/A

Date

Environmental Observations

Follow-up Status

16 Feb 2026

No major environmental deficiency was
observed.

N/A

March 2026

5 Mar 2026

No major environmental deficiency was
observed.

N/A

24 Mar 2026

No major environmental deficiency was
observed.

N/A

April 2026

13 Apr 2026

No major environmental deficiency was
observed.

N/A

29 Apr 2026

No major environmental deficiency was
observed.

N/A

Appendix E

Waste Flow Table

Name of Department: WSD Contract No.: 13/WSD/17

Monthly Summary Waste Flow Table for 2025 (year)

Month

Actual Quantities of Inert C&D Materials Generated Monthly

Actual Quantities of C&D Wastes Generated Monthly

Total Quantity
Generated

Hard Rock and
Large Broken
Concrete

Reused in the
Contract

Reused in other
Projects

Disposed as
Public Fill

Imported Fill

Metals

Paper/ cardboard
packaging

Plastics
(see Note 3)

Chemical
Waste

Others, e.g.
general refuse

(in '000kg)

(in '000kg)

(in '000kg)

(in '000kg)

(in '000kg)

(in '000kg)

(in '000 kg)

(in '000kg)

(in '000kg)

(in '000kg)

(in '000kg)

Jan

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

38.740

Feb

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

18.330

Mar

30.520

0.000

0.000

0.000

30.520

0.000

0.000

0.000

0.000

0.000

29.050

Apr

21.290

0.000

0.000

0.000

21.290

0.000

0.000

0.000

0.000

0.000

73.450

May

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

35.720

Jun

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

28.950

Sub-total

51.810

0.000

0.000

0.000

51.810

0.000

0.000

0.000

0.000

0.000

224.240

Jul

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

1.434

13.330

Aug

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

27.340

Sep

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

Oct

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

13.710

Nov

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

14.270

Dec

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

70.660

Total

51.810

0.000

0.000

0.000

51.810

0.000

0.000

0.000

0.000

1.434

363.550

Notes: (1) The performance targets are given in Section 1.69 of Specification B (2) The waste flow table shall also include C&D materials that are specified in the Contract to be imported for use at the Site.

(3) Plastics refer to plastic bottles/containers, plastic sheets/ foam from packaging material

Name of Department: WSD Contract No.: 13/WSD/17

Monthly Summary Waste Flow Table for 2026 (year)

Month

Actual Quantities of Inert C&D Materials Generated Monthly

Actual Quantities of C&D Wastes Generated Monthly

Total Quantity
Generated

Hard Rock and
Large Broken
Concrete

Reused in the
Contract

Reused in other
Projects

Disposed as
Public Fill

Imported Fill

Metals

Paper/ cardboard
packaging

Plastics
(see Note 3)

Chemical
Waste

Others, e.g.
general refuse

(in '000kg)

(in '000kg)

(in '000kg)

(in '000kg)

(in '000kg)

(in '000kg)

(in '000 kg)

(in '000kg)

(in '000kg)

(in '000kg)

(in '000kg)

Jan

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

22.300

Feb

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

18.070

Mar

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

66.120

Apr

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

88.530

May

Jun

Sub-total

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

195.020

Jul

Aug

Sep

Oct

Nov

Dec

Total

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

195.020

Notes: (1) The performance targets are given in Section 1.69 of Specification B (2) The waste flow table shall also include C&D materials that are specified in the Contract to be imported for use at the Site.

(3) Plastics refer to plastic bottles/containers, plastic sheets/ foam from packaging material

Appendix F

Summary of Exceedances

Table G1 Cumulative Statistics on Exceedances

Environmental
Monitoring

Parameter

No. of non-Project
related exceedance
in the reporting
period

Total No. of non-
Project related
exceedance in the
reporting period

No. of Project
related exceedance
in the reporting
period

Total No. of Project
related exceedance
in the reporting
period

Total No. recorded
since the project
commencement

AL

LL

AL

LL

Noise

L
eq (30min)

N/A

N/A

N/A

N/A

N/A

N/A

N/A

Water Quality

DO

0

0

0

0

0

0

0

Turbidity

0

0

0

0

0

0

0

SS

3

11

14

0

0

0

3237

pH

0

0

0

0

0

0

0

Landfill Gas

O
2

0

0

0

0

0

0

0

CH
4

0

0

0

0

0

0

0

CO
2

0

0

0

0

0

0

0

Appendix G

Complaint Log

Statistical Summary of Environmental Complaints

Reporting Period

Environmental Complaint Statistics

Frequency

Cumulative

Complaint Nature

1 May 2025
–
30 April 2026

0

3

Air Quality, Noise and Water
Quality

Statistical Summary of Environmental Summons

Reporting Period

Environmental Summons Statistics

Frequency

Cumulative

Details

1 May 2025
–
30 April 2026

0

0

N/A

Statistical Summary of Environmental Prosecution

Reporting Period

Environmental Prosecution Statistics

Frequency

Cumulative

Details

1 May 2025
–
30 April 2026

0

0

N/A

Appendix H

Event / Action Plan

Table I1 Event and Action Plan for Construction Noise Monitoring

Event

Action

ET

IEC

ER

Contractor

Action Level

1. Carry out investigation to identify the
source and cause of the complaint/
exceedance(s)
2. Notify IEC, ER, and Contractor and
report the results of investigation to the
Contractor, ER and the IEC
3. Discuss with the Contractor and IEC for
remedial measures required
4. If the complaint is related to the Project,
conduct additional monitoring for
checking mitigation effectiveness and
report the findings and results to the
IEC, ER and the Contractor

1. Review the analyzed results
submitted by the ET
2. Review the proposed remedial
measures by the Contractor and
advise the ER accordingly
3. Supervise the implementation of
remedial measures

1. Confirm receipt of Notification of
Exceedance in writing
2. Require Contractor to propose
remedial measures for
the analyzed noise problem
3. Ensure remedial measures are
properly implemented

1. Submit noise mitigation
proposals, if required, to
the IEC and ER
2. Implement noise
mitigation proposals

Limit Level

1. Carry out investigation to identify the
source and cause of the exceedance
2. Notify IEC, ER, Project Proponent, EPD
and Contractor
3. Repeat measurements to confirm
findings
4. Provide investigation report to IEC, ER,
EPD and Contractor he causes of the
exceedances
5. If the exceedance is related to the
Project, assess effectiveness by
additional monitoring
6. Report the remedial action
implemented and the additional
monitoring results to IEC, EPD, ER and
Contractor
7. If exceedance stops, cease additional
monitoring

1. Review the analyzed results
submitted by the ET
2. Discuss the potential remedial
measures with ER, ET Leader and
Contractor
3. Review Contractors remedial
actions whenever necessary to
assure their effectiveness and
advise the ER accordingly
4. Supervise the implementation of
remedial measures

1. Confirm receipt of Notification of
Exceedance in writing
2. Require the Contractor to propose
remedial measures for the
analyzed noise problem
3. Ensure remedial measures are
properly implemented
4. If exceedance continues, consider
what activity of the work is
responsible and instruct the
Contractor, in agreement with the
Project Proponent, to stop that
activity of work until the exceedance
is abated

1. Take immediate action to
avoid further exceedance
2. Submit proposals for
remedial actions to IEC
and ER within 3 working
days of notification
3. Implement the agreed
proposals
4. Resubmit proposals if
problem still not under
control
5. Stop the relevant activity
of works as determined
by the Project Proponent
until the exceedance is
abated

Table I2 Event and Action Plan for Water Quality Monitoring

Event

Action

ET

IEC

Contract(s)

ER

Action Level
being exceeded
by one sampling
day

1. Repeat in situ measurement on the
next day of exceedance to confirm
findings;
2. Check monitoring data, plant,
equipment and Contractor(s)’s
working methods;
3. Identify source(s) of impact and
record in notification of exceedance;
4. Inform IEC, Contractor(s) and ER.

1. Check monitoring data
submitted by ET and
Contractor(s)’s working
methods;
2. Inform EPD.

1. Confirm receipt of notification of
exceedance in writing;
2. Check plant and equipment and
rectify unacceptable practice

1. Confirm receipt of notification of
exceedance in writing.

Action Level
being exceeded
by two or more
consecutive
sampling days

1. Repeat in situ measurement on the
next day of exceedance to confirm
findings;
2. Check monitoring data, plant,
equipment and Contractor(s)’s
working methods;
3. Identify source(s) of impact and
record in notification of exceedance;
4. Inform IEC, Contractor(s) and ER;
5. Discuss with IEC and Contractor(s) on
additional mitigation measures and
ensure that they are implemented

1. Check monitoring data
submitted by ET and
Contractor(s)’s working
methods;
2. Inform EPD;
3. Discuss with ET and
Contractor(s) on additional
mitigation measures and
advise ER accordingly;
4. Assess the effectiveness of the
implemented mitigation
measures

1. Confirm receipt of notification of
exceedance in writing;
2. Check plant and equipment and
rectify unacceptable practice;
3. Consider changes of working
methods;
4. Discuss with ET and IEC on
additional mitigation measures
and propose them to ER within 3
working days;
5. Implement the agreed

1. Confirm receipt of notification of
exceedance in writing;
2. Discuss with the IEC on the
proposed additional mitigation
measures and agree on the
mitigation measures to be
implemented.
3. Ensure additional mitigation
measures are properly
implemented.

Limit Level being
exceeded by one
sampling day

4. Repeat in situ measurement on the
next day of exceedance to confirm
findings;
5. Check monitoring data, plant,
equipment and Contractor(s)’s
working methods;
6. Identify source(s) of impact and
record in notification of exceedance;
7. Inform IEC, Contractor(s) and ER;
8. Discuss with IEC and Contractor(s) on
additional mitigation measures and
ensure that they are implemented

1. Check monitoring data
submitted by ET and
Contractor(s)’s working
methods;
2. Inform EPD;
3. Discuss with ET and
Contractor(s) on additional
mitigation measures and
advise ER accordingly;
4. Assess the effectiveness of the
implemented mitigation
measures.

1. Confirm receipt of notification of
exceedance in writing;
2. Check plant and equipment and
rectify unacceptable practice;
3. Critically review the need to
change working methods;
4. Discuss with ET and IEC on
additional mitigation measures
and propose them to ER within 3
working days;
5. Implement the agreed

1. Confirm receipt of notification of
exceedance in writing;
2. Discuss with the IEC on the
proposed additional mitigation
measures and agree on the
mitigation measures to be
implemented.
3. Ensure additional mitigation
measures are properly
implemented.
4. Request Contractor(s) to critically
review the working methods.

Event

Action

ET

IEC

Contract(s)

ER

Limit Level being
exceeded by two
or more
consecutive
sampling days

1. Repeat in situ measurement on the
next day of exceedance to confirm
findings;
2. Check monitoring data, plant,
equipment and Contractor(s)’s
working methods;
3. Identify source(s) of impact and
record in notification of exceedance;
4. Inform IEC, Contractor(s) and ER;
5. Discuss with IEC and Contractor(s) on
additional mitigation measures and
ensure that they are implemented

1. Check monitoring data
submitted by ET and
Contractor(s)’s working
methods;
2. Inform EPD;
3. Discuss with ET and
Contractor(s) on additional
mitigation measures and
advise ER accordingly;
4. Assess the effectiveness of the
implemented mitigation
measures.

1. Confirm receipt of notification of
exceedance in writing;
2. Check plant and equipment and
rectify unacceptable practice;
3. Critically review the need to
change working methods;
4. Discuss with ET and IEC on
additional mitigation measures
and propose them to ER within 3
working days;
5. Implement the agreed
mitigation measures.
6. As directed by ER, slow down or
stop all or part of the marine
construction
works/ production volume of
the desalination plant until no
exceedance of Limit Level.

1. Confirm receipt of notification of
exceedance in writing;
2. Discuss with the IEC on the
proposed additional mitigation
measures and agree on the
mitigation measures to be
implemented.
3. Ensure additional mitigation
measures are properly
implemented.
4. Request Contractor(s) to critically
review the working methods;
5. Consider and instruct, if necessary,
the Contractor(s) to slow down or
to stop all or part of the marine
construction
works/production volume of the
desalination plant until no
exceedance of Limit Level.