Revision History
Rev. |
Description of Modification |
Date |
1. |
First Issue for Comments |
05/06/2024 |
2. |
Revised According to Comments |
12/06/2024 |
3. |
Revised According to Comments |
12/06/2024 |
CONTENTS
9. Summary of Exceedance, Complaints, Notification of Summons and Prosecutions.............. 40
Appendix A Master Programme
Appendix B Overview of Desalination Plant in Tseung Kwan O
Appendix C Summary of Implementation Status of Environmental Mitigation
Appendix D Impact Monitoring Schedule
Appendix E Event/Action Plan
Appendix F Water Quality Monitoring Equipment and Landfill Gas Equipment Calibration Certificate
Appendix G Water Quality Monitoring Data and Landfill Gas Monitoring Data
Appendix H Waste Flow Table
Appendix I Ecology (Coral & Fishery) Survey Report
Appendix J Site Inspection Proforma
Appendix K Complaint Log
Appendix L Exceedance
Report
Executive Summary
Introduction
A1. The Project, Design, Build and Operate First Stage of Tseung Kwan O Desalination Plant (TKODP), is a Designated Project under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO) and is currently governed by a Further Environmental Permit (EP No. FEP - 01/503/2015/B) for the construction and operation of the Contract.
A2. In accordance with the Environmental Monitoring and Audit (EM&A) Manual for the Contract, EM&A works for marine water quality, noise, waste management and ecology should be carried out by Environmental Team (ET), Acuity Sustainability Consulting Limited (ASCL), during the construction phase of the Contract.
A3. This is the 51st Monthly EM&A Report, prepared by ASCL, for the Contract summarizing the monitoring results and audit findings of the EM&A programme at and around Tseung Kwan O Area 137 (TKO 137) during the reporting period from 1 May to 31 May 2024.
A4. The EM&A programme for this contract has covered environmental monitoring on construction noise level at selected NSRs and Contractor¡¦s environmental performance auditing in the aspects of construction dust, construction noise, water quality, waste management, Landscape and Visual and Ecology.
Summary of Main Works Undertaken & Key Mitigation Measures Implemented
A5. Key activities carried out in this reporting period for the Contract included the followings:
Administration Building - Installation of ceiling - Painting works - Installation of sanitary fitting - Installation of vinyl flooring - Installation of Aluminium Fins - Installation of Internal partition wall and ceiling - External wall finishing works - Installation of AP doors and cat ladders - Installation of wood decking - Minor Installation of building services, cable laying and termination, Photovoltaic Panel Installation, Testing & Commissioning |
Chemical building - External wall painting works - Defect rectification |
Main Electrical & Central Chiller Plant Building - Minor Installation of building services, electrical switchboard, cable laying, pressure test - Ladder and Cover installation at Roof |
ActiDAFF - Sealing gap and wall openings - Installation of signage - Minor Installation of mechanical equipment, building services, minor cable laying and termination, Installation of Fibre Reinforced Polymer Cover, Testing & Commissioning |
Product Water Storage Tank Building - Installation of signage - Installation of cladding works - Tiling work at Roof Slab on Tank A - Ladder and Cover installation at Roof - Roof Tiles installation - Minor Installation of building services, cable laying and termination, Testing & Commissioning |
OSCG Building - Core Opening at Cladding - Installation of cladding works - Installation of Railing on Brine Maker Tank - Installation of building services, mechanical equipment and cable laying and termination, testing and commissioning and pressure test |
Reverse Osmosis Building - Installation of AP doors - Installation of sanitary fitting - Sanitary Ware Installation in Toilet - Tiling Work in Toilet - Installation of Water Meter Cabinets - Installation of building services, electrical switchboard of cable laying and termination, Minor Installation of mechanical equipment and raised floor, testing and commissioning, Photovoltaic Panel Installation |
Post Treatment Building - DFMA Gap Seal Up - Minor Installation of building services, Minor Installation of mechanical equipment, Cable laying and termination, Pressure Test |
Inspection corridor - Interior painting works - Interior fitting out works |
Combined Shaft and Pump room - Installation of outfall grating and defect rectification . - Minor cable laying and termination, testing and commissioning Guard House - Guard house A defect rectification - Guard house B defect rectification - Minor Cable laying and Termination Slope
Work (Suspended due to landslides occurred during the rainstorm since
4 May 2024) - Rock Dowel Installation - Buttress Construction - Wire Mesh Laying - Drilling; Rock anchors installation, Rock break, Concreting Other - Watermain installation works at CLP 132 Kv Substation - Underground utility rectification work for Manhole and Draw pit - Underground utility Construction Work for Watermain water - Underground utility repair Work for Sewerage, Watermains work - Security Fence footing construction work - Light Pole installation work - Road Construction - Footpath Construction - Landscape Construction - Irrigation System installation - Landscape planting work - Traffic signage work - Workshop construction work, Tiling work, green roof and irrigation pipe - Workshop Building Services Installation, cable laying and termination - Tiling work and cladding installation for Elevated Walkway - Master meter defect rectification - Wave deflector Wall |
A6. The major environmental impacts brought by the above construction works include:
- Construction dust and noise generation from construction works, excavation works and slope works;
- Waste generation from the construction activities
A7. The key environmental mitigation measures implemented for the Contract in this reporting period associated with the above construction works include:
- Dust suppression by regular wetting and water spraying for construction works;
- Reduction of noise from equipment and machinery on-site and regular inspection to machinery and plants/vehicles on-site to ensure proper functioning;
- Deployment of silt curtain at the inshore water outflow;
- Sorting and storage of general refuse and construction waste; and
-
Deployment protective fencing
for trees
Summary of exceedance & investigation &
follow-up
A8. No noise monitoring was conducted during the reporting period since there are no Contract -related construction activities undertaken within a radius of 300m from the monitoring locations. No exceedance of the action Level was recorded during the reporting period.
A9. The construction phase marine water quality programme was ceased from 1 September 2023 due to the completion of marine-related construction works.
A10. The EM&A works for Pre-operation phase marine water quality were conducted during the reporting period in accordance with the EM&A Manual. Sixteen (16) of the pre- operation phase water quality monitoring results of SS obtained had exceeded the Action Level. Nine (9) of the pre-operation phase water quality monitoring results of SS obtained during the reporting period had exceeded the Limit Level.
A11. Water quality monitoring of the discharge of dechlorinated effluent in disinfection procedure is completed in December 2023. The hourly dechlorinated effluent monitoring during the discharge is finished.
A12. Pre-operation phase coral monitoring works
was conducted on 17 May 2024. There is no AL/LL
exceedance during the monitoring period. The detail of the monitoring is
presented in Appendix I
A13. Pre-operation phase fishery monitoring for dry season 2024 was carried out on 17 and 24 February 2024. The detail of the monitoring is presented in the 50th Monthly EM&A Report.
A14. In this reporting period, 96 times of landfill gas monitoring were periodically conducted at TKO Area 137 (Ch1+120 - Ch1+800). No exceedances of action level and limit level was observed.
A15. Joint site inspections of the construction work by ET and IEC were carried out on 28 May 2024 to audit the mitigation measures implementation status. Reminders were recorded in the site inspection checklists and provided to the contractors together with the appropriate follow-up actions where necessary.
Complaint Handling and Prosecution
A16. No environmental complaint, notification of summons and prosecution was received in the reporting period.
Reporting Change
A17. There was no change to be reported that may affect the on-going EM&A programme.
Summary of Upcoming
Key Issues and Key Mitigation Measures
A18. Key activities anticipated in the next reporting period for the Contract will include the followings:
Administration Building - Installation of ceiling, door - Painting works - Tiling works - Wall finishing works - External wall finishing works - Installation of AP doors and cat ladders - Installation of Internal partition wall and ceiling - Installation of wood decking - Minor Installation of building services, cable laying and termination, Photovoltaic Panel Installation, Testing & Commissioning |
Chemical building - External wall painting works - Defect rectification |
Main Electrical & Central Chiller Plant Building - Installation of signage - Minor Installation of building services, electrical switchboard, cable laying, pressure test |
ActiDAFF - Sealing gap and wall openings - Installation of signage - Minor Installation of mechanical equipment, building services, minor cable laying and termination, Installation of Fibre Reinforced Polymer Cover, Testing & Commissioning |
Product Water Storage Tank Building - Installation of signage - Opening Seal Up - Tiling work at Roof Slab on Tank A - Minor Installation of building services, cable laying and termination, Testing & Commissioning |
OSCG Building - Installation of Railing on Brine Maker Tank - Core Opening at DFMA - Minor Installation of building services and pipework, cable laying and termination, and commissioning and pressure test |
Reverse Osmosis Building - Sanitary Ware Installation in Toilet - Opening Seal Up - Installation of Water Meter Cabinets - Installation of signage - Minor Installation of building services, cable laying and termination , testing and commissioning, Photovoltaic Panel Installation |
Post Treatment Building - Installation of signage - DFMA Gap Seal Up - Installation of Railing near Staircase - Minor Installation of building services, Minor Installation of pipework, Cable laying and termination |
Inspection corridor - Interior painting works - Interior fitting out works |
Combined Shaft and Pump room - Installation of outfall grating and defect rectification . - Testing and commissioning Guard House - Guard house A defect rectification - Guard house B defect rectification - Building Services Installation, cable laying and termination Other - Watermain installation works at CLP 132 Kv Substation - Underground utility rectification work for Manhole and Draw pit - Underground utility Construction Work for Watermain water - Underground utility repair Work for Sewerage, Watermains work - Underground utility repair work (sampling pipe) - Security Fence footing construction work - Light Pole installation work - Road Construction - Footpath Construction - Landscape Construction - Irrigation System installation - Landscape planting work |
- Workshop construction work, Tiling work, green roof and irrigation pipe - Workshop Building Services Installation, cable laying and termination - Tiling work, glass balustrade and cladding installation for Elevated Walkway - Master meter defect rectification - Wave deflector Wall |
A19. The major environmental impacts brought by the above construction works will include:
- Construction dust and noise generation from excavation, construction works and slope works; and
- Waste generation from construction activities.
A20. The key environmental mitigation measures for the Contract in the coming reporting period associated with the above construction works will include:
- Reduction of noise from equipment and machinery on-site;
- Dust suppression by regular wetting and water spraying for construction works and at main haul road;
- Sorting and storage of general refuse and construction waste;
- Deployment of silt curtain at the inshore water outflow; and
-
Deployment protective fencing
for trees.
Background
1.1. The Acciona Agua, S.A. Trading, Jardine Engineering Corporation, Limited and China State Construction Engineering (Hong Kong) Limited as AJC Joint Venture (AJCJV) is contracted to carry out the Design, Build and Operate First Stage of Tseung Kwan O Desalination Plant (DPTKO) under Contract No. 13/WSD/17 (the Contract).
1.2. Acuity Sustainability Consulting Limited (ASCL) is commissioned by AJCJV to undertake the Environmental Team (ET) services as required and/or implied, both explicitly and implicitly, in the Environmental Permit (EP), Environmental Impact Assessment Report (EIA Report) (Register No. AEIAR-192/2015) and Environmental Monitoring and Audit Manual (EM&A Manual) for the Contract; and to carry out the Environmental Monitoring and Audit (EM&A) programme in fulfillment of the EIA Report¡¦s EM&A requirements and Contract No. 13/WSD/17 Specification requirements.
1.3. Pursuant to the Environmental Impact Assessment Ordinance (EIAO), the Director of Environmental Protection granted the Environmental Permit (No. EP-503/2015/B) to Water Supplies Department (WSD); and granted the Further Environmental Permit (No. FEP-01/503/2015/B) to AJCJV for the Contract.
The Reporting Scope
1.4. This is the 51st Monthly EM&A Report for the Contract which summarizes the key findings of the EM&A programme during the reporting period from 1 May to 31 May 2024.
Contract Organization
1.5. The Contract Organization structure for Construction Phase is presented in Figure 1.1.
Figure 1.1 Contract Organization Chart
1.6. Contact details of the key personnel are presented in Table 1.1 below:
Table 1.1 Contact Details
of Key Personnel
Party |
Position |
Name |
Telephone no. |
Contract Proponent (Water Supplies Department) |
SE/CM2 |
Milton Law |
2634-3573 |
Supervising Officer (Binnies Hong Kong Limited) |
Project Manager |
Christina Ko |
2608-7302 |
Chief Resident
Engineer |
Roger Wu |
6343-1002 |
|
The Jardine
Engineering Corporation, Limited, China
State Construction Engineering (Hong Kong) Limited and Acciona Agua, S.A. Trading |
Project Manager |
Stephen Yeung |
2807-4665 |
Environmental
Monitoring Manager |
Brian Kam |
9456-9541 |
|
Environmental
Monitoring Manager |
Tommy Law |
6468-1782 |
|
Acuity Sustainability Consulting Limited |
Environmental Team Leader |
Toby Wan |
9719-5422 |
Lam Environmental Services Limited |
Independent Environmental Checker
(IEC) |
Serena Shek |
6149-6683 |
Summary of Construction Works
1.7. Details of the major construction activities undertaken in this reporting period are shown below. The master programme is presented in Appendix A.
1.8. Key activities carried out in this reporting period for the Contract included the followings:
Administration Building - Installation of ceiling - Painting works - Installation of sanitary fitting - Installation of vinyl flooring - Installation of Aluminium Fins - Installation of Internal partition wall and ceiling - External wall finishing works - Installation of AP doors and cat ladders - Installation of wood decking - Minor Installation of building services, cable laying and termination, Photovoltaic Panel Installation, Testing & Commissioning |
Chemical building - External wall painting works - Defect rectification |
Main Electrical & Central Chiller Plant Building - Minor Installation of building services, electrical switchboard, cable laying, pressure test - Ladder and Cover installation at Roof |
ActiDAFF - Sealing gap and wall openings - Installation of signage - Minor Installation of mechanical equipment, building services, minor cable laying and termination, Installation of Fibre Reinforced Polymer Cover, Testing & Commissioning |
Product Water Storage Tank Building - Installation of signage - Installation of cladding works - Tiling work at Roof Slab on Tank A - Ladder and Cover installation at Roof - Roof Tiles installation - Minor Installation of building services, cable laying and termination, Testing & Commissioning |
OSCG Building - Core Opening at Cladding - Installation of cladding works - Installation of Railing on Brine Maker Tank - Installation of building services, mechanical equipment and cable laying and termination, testing and commissioning and pressure test |
Reverse Osmosis Building - Installation of AP doors - Installation of sanitary fitting - Sanitary Ware Installation in Toilet - Tiling Work in Toilet - Installation of Water Meter Cabinets - Installation of building services, electrical switchboard of cable laying and termination, Minor Installation of mechanical equipment and raised floor, testing and commissioning, Photovoltaic Panel Installation |
Post Treatment Building - DFMA Gap Seal Up - Minor Installation of building services, Minor Installation of mechanical equipment, Cable laying and termination, Pressure Test |
Inspection corridor - Interior painting works - Interior fitting out works |
Combined Shaft and Pump room - Installation of outfall grating and defect rectification . - Minor cable laying and termination, testing and commissioning Guard House - Guard house A defect rectification - Guard house B defect rectification - Minor Cable laying and Termination Slope
Work (Suspended due to landslides occurred during the rainstorm since
4 May 2024) - Rock Dowel Installation - Buttress Construction - Wire Mesh Laying - Drilling; Rock anchors installation, Rock break, Concreting Other - Watermain installation works at CLP 132 Kv Substation - Underground utility rectification work for Manhole and Draw pit - Underground utility Construction Work for Watermain water - Underground utility repair Work for Sewerage, Watermains work - Security Fence footing construction work - Light Pole installation work - Road Construction - Footpath Construction - Landscape Construction - Irrigation System installation - Landscape planting work - Traffic signage work - Workshop construction work, Tiling work, green roof and irrigation pipe - Workshop Building Services Installation, cable laying and termination - Tiling work and cladding installation for Elevated Walkway - Master meter defect rectification - Wave deflector Wall |
1.9. A summary of the valid permits, licences, and/or notifications on environmental protection for this Contract is presented in Table 1.2.
Table 1.2 Summary
of the Status of Valid Environmental Licence,
Notification, Permit and Documentations
Permit/ Licences |
Valid Period |
Status |
Remark |
|
From |
To |
|||
Environmental Permit |
||||
EP-503/2015/B |
Throughout the Contract |
Valid |
|
|
FEP - 01/503/2015/B |
Throughout the Contract |
Valid |
|
|
Notification of Construction Works
under the Air Pollution Control
(Construction Dust) Regulation (Form NA) |
||||
451539 |
Throughout the Contract |
Valid |
- |
|
Billing Account
for Disposal of Construction Waste |
||||
7036276 |
Throughout the Contract |
Valid |
- |
|
Sludge (Special Waste) Disposal (Admission Ticket) |
||||
17674 |
04/01/2024 |
30/06/2024 |
Valid |
- The renewal application of ¡§Sludge (Special Waste) Disposal (Admission Ticket)¡¨ was submitted. |
Chemical Waste
Producer Registration |
||||
5213-839-A2987-01 |
Throughout the Contract |
Valid |
- |
|
Wastewater Discharge Licence (Land and Marine
works) |
||||
WT00035775-2020 |
23/08/2021 |
31/07/2025 |
Valid |
- |
WT00044188-2023 |
16/06/2023 |
30/06/2028 |
Valid |
- For Plant T&C and operation. - Variation of sampling point for the Discharge Licence Part 1 is in process. |
Construction Noise
Permit |
||||
GW-RE1514-23 |
22/12/2023 |
21/06/2024 |
Valid |
-Renewal of CNP is in process. |
1.10. The status for all environmental aspects is presented in Table 1.3.
Table 1.3 Summary
of Status for Key Environmental Aspects under the EM&A Manual
Parameters |
Status |
Water Quality |
|
Baseline Monitoring under EM&A Manual |
The baseline water quality monitoring was conducted between 12 May 2020 to 6 June 2020. |
Construction Phase Impact Monitoring |
Ceased from 1 September 2023 |
Pre-operation phase Marine Impact Monitoring |
On-going |
Impact Monitoring of Effluent Discharge from Main Disinfection |
Completed |
Noise |
|
Baseline Monitoring |
The baseline noise monitoring result has been reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4 |
Impact Monitoring |
Completed |
Waste Management |
|
Mitigation Measures in Waste Management Plan |
On-going |
Landfill Gas |
|
Regular Monitoring when construction works are within the 250 m Consultation Zone |
On-going |
Ecology (Coral) |
|
Pre-operation phase Regular Coral Monitoring (Monthly) |
On-going |
Ecology (Fishery) |
|
Pre-operation phase Regular Fishery Monitoring (Seasonally) |
On-going |
Ecology (Landscape) |
|
Pre-operation phase Landscape and Visual Site Inspection |
On-going |
Environmental Audit |
|
Site Inspection covering Measures of Air Quality, Noise Impact, Water Quality, Waste, Ecological Quality, Fisheries, Landscape and Visual |
On-going |
1.11. Other than the EM&A work by ET, environmental briefings, trainings, and regular environmental management meetings were conducted, in order to enhance environmental awareness and closely monitor the environmental performance of the contractors.
1.12. The EM&A programme has been implemented in accordance with the recommendations presented in the approved EIA Report and the EM&A Manual. A summary of implementation status of the environmental mitigation measures for the construction phase and the Pre-operation phase of the Contract during the reporting period is provided in Appendix C.
Monitoring Requirements
2.1. To ensure no adverse noise impact, noise monitoring is recommended to be carried out within 300m radius from the nearby noise sensitive receivers (NSRs), during construction phase. The NSRs selected as monitoring station are (i) NSR4 - Creative Secondary School,
(ii) NSR24 - PLK Laws Foundation College, and (iii) NSR31 - School of Continuing and Professional Studies - CUHK respectively.
2.2. Construction noise level were measured in terms of the A-weighted equivalent continuous sound pressure level (LAeq). Leq 30min was used as the monitoring parameter for the time period between 0700 and 1900 on normal weekdays. Construction works would follow stipulations of the valid Construction Noise Permits if works had to be conducted during restricted hours or public holidays. Table 2.1 summarizes the monitoring parameters, frequency, and duration of the impact noise monitoring.
Table 2.1 Noise Monitoring Parameters, Time, Frequency and Duration
Time |
Duration |
Interval |
Parameters |
Daytime: 0700-1900 |
Day time: 0700-1900 (during normal weekdays) |
Continuously in Leq 5min/Leq 30min (average of 6 consecutive Leq 5min) |
Leq 30min L10 30min & L90 30min |
Monitoring Locations
2.3. The monitoring locations were normally made at a point 1m from the exterior of the NSRs building façade and be at a position 1.2m above the ground. A correction of +3dB(A) should be made to the free-field measurements.
2.4. According to the environmental findings detailed in the EIA report and Baseline Monitoring Report, the designated locations for the construction noise monitoring are listed in Table 2.2 below.
Table 2.2 Noise Sensitive Receivers
NSR ID |
Noise Sensitive Receivers |
Monitoring Location |
Position |
NSR 4 |
Creative Secondary School |
Roof Floor |
1 m from facade |
NSR 24 |
PLK Laws Foundation College |
Pedestrian Road on Ground Floor |
Free-field |
NSR 31 |
School of Continuing and Professional Studies - CUHK |
Roof Floor |
1 m from facade |
2.5. Three noise monitoring locations for impact monitoring at the nearby sensitive receivers are shown in Figure 2.1-2.3.
|
Figure 2.1 NSR4
Creative Secondary School |
|
Figure 2.2 NSR24
PLK Laws Foundation College |
|
Figure 2.3
NSR31 School of Continuing and Professional Studies - CUHK |
Impact Monitoring Methodology
2.6. Integrated sound level meter will be used for the noise monitoring. The meter will be in compliance with the International Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications. Immediately prior to and following each noise measurement the accuracy of the sound level meter will be checked using an acoustic calibrator generating a known sound pressure level at a known frequency. Measurements will be accepted as valid only if the calibration levels before and after the noise measurements agree to within 1.0 dB(A).
2.7. Noise measurements were not made in the presence of fog, rain, wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with a portable wind speed meter capable of measuring the wind speed in m/s.
Action and Limit Levels
2.8. The Action/Limit Levels are in line with the criteria of Practice Note for Professional Persons (ProPECC PN 2/93) ¡§Noise from Construction Activities - Non-statutory Controls¡¨ and Technical Memorandum on Environmental Impact Assessment Process issued by HKSAR Environmental Protection Department [¡§EPD¡¨] under the Environmental Impact Assessment Ordinance, Cap 499, S.16 are presented in Table 2.3.
Table 2.3 Action and Limit Levels
for Noise per EM&A Manual
Time Period |
Action |
Limit (dB(A)) |
0700-1900 on normal weekdays |
When one documented complaint is received from any one of the noise sensitive receivers |
- 70 dB(A) for school and - 65 dB(A) during examination period |
Note: Limits specified in the GW-TM and IND-TM for construction and operation noise,
respectively.
2.9.
If exceedances were found
during noise monitoring, the actions in accordance with the Event and Action
Plan shall be carried out according to Appendix
E.
Monitoring Results
and Observations
2.10. Referring to EM&A Manual Section 4.1.2, the impact noise monitoring should be carried out when there are Contract-related construction activities undertaken within a radius of 300m from the monitoring stations. As no Contract-related construction activities were undertaken in the reporting month within a radius of 300m from the monitoring stations as shown in Figure 2.4, no impact noise monitoring was conducted in the reporting period.
Figure 2.4 Site Layout Plan with Noise Sensitive Receivers and Desalination Plant
3.1. In accordance with the recommendations of the EIA, water quality monitoring is required during dredging for the submarine pipelines and, during operation phase. The following Section provides details of the water quality monitoring to be undertaken by the Environmental Team (ET) to verify the distance of sediment and brine plume dispersion and to identify whether the potential exists for any indirect impacts to occur to ecological sensitive receivers.
3.2. The water quality monitoring programme was be carried out to allow any deteriorating water quality to be readily detected and timely action taken to rectify the situation.
3.3. Water quality monitoring for the Contract can be divided into the following stages:
- Dredging activities during construction phase;
- Discharge of effluent from main disinfection during construction phase; and
- Operation activities during Pre-operation phase.
Water Quality
Parameters
3.4. The parameters that have been selected for measurement in situ and in the laboratory are those that were either determined in the EIA to be those with the most potential to be affected by the construction works or are a standard check on water quality conditions. Parameters to be measured in the impact monitoring are listed in Table 3.1.
Table 3.1 Parameters measured
in the Impact Marine Water Quality Monitoring
Parameters |
Unit |
Abbreviation |
In-situ measurements |
||
Dissolved oxygen |
mg/L |
DO |
Temperature |
oC |
- |
pH |
- |
- |
Turbidity |
NTU |
- |
Salinity |
0/00 |
- |
Total Residual Chlorine NOTE1 |
mg/L |
TRC |
Laboratory measurements |
||
Suspended Solids |
mg/L |
SS |
Iron-Soluble |
mg/L |
Fe |
Anti-scalant as Reactive Phosphorus |
mg/L |
PO4 as P- |
NOTE 1: Monitoring of Total Residual
Chlorine will be conducted when cleaning and sterilization of the new freshwater main is carried out.
3.5. In addition to the water quality parameters, other relevant data were also being measured and recorded in Water Quality Monitoring Logs, including the location of the sampling stations, water depth, time, weather conditions, sea conditions, tidal stage, current direction and velocity, special phenomena and work activities undertaken around the monitoring and works area that may influence the monitoring results.
Monitoring Equipment
3.6. For water quality monitoring, the following equipment were used:
Dissolved Oxygen and Temperature Measuring Equipment - The instrument was a portable, weatherproof dissolved oxygen measuring instrument complete with cable, sensor, comprehensive operation manuals, and was operable from a DC power source. It was capable of measuring: dissolved oxygen levels in the range of 0 - 20 mg/L and 0 - 200% saturation; and a temperature of 0 - 45 degrees Celsius. It has a membrane electrode with automatic temperature compensation complete with a cable of not less than 35 m in length. Sufficient stocks of spare electrodes and cables were available for replacement where necessary (e.g. YSI model 59 DO meter, YSI 5739 probe, YSI 5795A submersible stirrer with reel and cable or an approved similar instrument).
Turbidity Measurement Equipment - The instrument was a portable, weatherproof turbidity-measuring unit complete with cable, sensor and comprehensive operation manuals. The equipment was operated from a DC power source, it has a photoelectric sensor capable of measuring turbidity between 0 - 1000 NTU and complete with a cable with at least 35 m in length (for example Hach 2100P or an approved similar instrument).
Salinity Measurement Instrument - A portable salinometer capable of measuring salinity in the range of 0 - 40 ppt was provided for measuring salinity of the water at each monitoring location.
Water Depth Gauge - A portable, battery-operated echo sounder (for example Seafarer 700 or a similar approved instrument) was used for the determination of water depth at each designated monitoring station. This unit will preferably be affixed to the bottom of the work boat if the same vessel is to be used throughout the monitoring programme. The echo sounder was suitably calibrated.
Positioning Device - A Global Positioning System (GPS) was used during monitoring to allow accurate recording of the position of the monitoring vessel before taking measurements. The Differential GPS, or equivalent instrument, was suitably calibrated at appropriate checkpoint (e.g. Quarry Bay Survey Nail) to verify that the monitoring station is at the correct position before the water quality monitoring commence.
Water Sampling Equipment - A water sampler, consisting of a PVC or glass cylinder of not less than two litres, which can be effectively sealed with cups at both ends, was used. The water sampler has a positive latching system to keep it open and prevent premature closure until released by a messenger when the sampler is at the selected water depth.
Total Residual Chlorine -Total residual chlorine (TRC) shall be measured in-situ using approved test kit.
Sampling / Testing Protocols
3.7. All in situ monitoring instruments were checked, calibrated, and certified by a laboratory accredited under HOKLAS or any other international accreditation scheme before use, and subsequently re-calibrated at monthly intervals throughout the stages of the water quality monitoring. Responses of sensors and electrodes were checked with certified standard solutions before each use.
3.8. On-site calibration of field equipment was following the ¡§Guide to On-Site Test Methods for the Analysis of Waters¡¨, BS 1427: 2009. Sufficient stocks of spare parts were maintained for replacements when necessary. Backup monitoring equipment was made available so that monitoring can proceed uninterrupted even when equipment is under maintenance, calibration etc.
Laboratory Measurement and Analysis
3.9. Sufficient volume of each water sample was collected for carrying out the laboratory analyses. Using chain of custody forms, collected water samples were transferred to a HOKLAS accredited laboratory (Acumen Laboratory and Testing Limit - HOKLAS 241) for immediate processing. The determination work was start within the next working day after collection of the water samples. Analytical methodology and sample preservation of other parameters were based on the latest edition of Standard Methods for the Examination of Waste and Wastewater published by APHA, AWWA and WPCF and methods by USEPA, or suitable method in accordance with requirements of HOKLAS or another internationally accredited scheme. The QA/QC details were in accordance with the requirements of HOKLAS or another internationally accredited scheme.
3.10. Parameters for laboratory measurements, standard methods and detection limits are presented in Table 3.2.
Table 3.2 Laboratory measurements, standard methods, and corresponding
detection limits of marine water quality monitoring
Parameters |
Standard Methods |
Detection Limit |
Reporting Limit |
Precision |
Dissolved oxygen |
Instrumental, CTD |
0.1 |
- |
+-25% |
Temperature |
Instrumental, CTD |
0.1 |
- |
+-25% |
pH |
Instrumental, CTD |
0.1 |
- |
+-25% |
Turbidity |
Instrumental, CTD |
0.1 |
- |
+-25% |
Salinity |
Instrumental, CTD |
0.1 |
- |
+-25% |
Suspended Solids |
APHA 23rd Ed 2540D |
1.0 |
2.5 |
+-17% |
Iron |
APHA 3111 B |
0.2 |
- |
+-25% |
Total residual chlorine |
Test Kit (Lovibond MD200) |
Lowest limit
= 0.01mg/L; Upper limit
= 6 mg/L |
- |
+-25% |
Monitoring Location
Construction Phase
3.11. The Impact water quality monitoring was ceased from 1 September 2023 due to the completion of marine-related construction works.
Pre-operation phase
3.12. The pre-operation phase impact water quality monitoring locations are in accordance with the EM&A Manual and detailed in Table 3.3 below. A schedule for water quality monitoring was prepared by the ET and submitted to IEC and EPD prior to the commencement of the monitoring.
Table 3.3 Location
of Impact Water Quality Monitoring Stations
Station |
Easting |
Northing |
Description |
CE |
843550 |
815243 |
Upstream control station at ebb tide |
CF |
846843 |
810193 |
Upstream control station at flood tide |
WSR1 |
846864 |
812014 |
Ecological sensitive receiver at Tung Lung Chau |
WSR2 |
847645 |
812993 |
Fisheries sensitive receiver at Tung Lung Chau |
WSR3 |
848023 |
813262 |
Ecological sensitive receiver at Tung Lung Chau |
WSR4 |
847886 |
814154 |
Ecological sensitive receiver at Tai Miu Wan |
WSR16 |
845039 |
815287 |
Ecological sensitive receiver at Fat Tong Chau |
WSR33 |
847159 |
814488 |
Ecological sensitive receiver at Tai Miu Wan |
WSR36 |
846878 |
814081 |
Ecological sensitive receiver at Kwun Tsai |
WSR37 |
846655 |
813810 |
Ecological sensitive receiver at Tit Cham Chau |
NF1 |
846542 |
813614 |
Edge of Mixing zone, ~ 200m west of outfall diffuser |
NF2 |
846942 |
813614 |
Edge of Mixing zone, ~ 200m east of outfall diffuser |
NF3 |
846742 |
813414 |
Edge of Mixing zone, ~ 200m south of outfall diffuser |
3.13. WSR1 to WSR37 were identified in accordance with Annex 14 of the EIAO-TM as well as Clause 3.4.4.2 of the Environmental Impact Assessment Study Brief for Desalination Plant at Tseung Kwan O (No. ESB-266/2013). WSR1 to WSR3 are sited near the Tung Lung Chau Fish Culture Zone; WSR16 and WSR36 are sited near the coral assemblages along the coastlines of Fat Tong Chau and Kwun Tsai respectively; WSR 4 and WSR33 are sited near the Coastal Protection Area and coral assemblages in waters of Tai Miu Wan; WSR37 is sited near the fisheries resource including spawning and nursery grounds at the coastal water of Tit Cham Chau. NF1 to NF3 are the Edge of Mixing zone.
Figure 3.1 Impact water quality
monitoring locations under EM&A Manual
Sampling Frequency
Pre-operation phase
3.14. Impact water quality monitoring were carried out three days per week during the commission phase. Monitoring at each station was undertaken once per day. The interval between two sets of monitoring was not less than 36 hours. The monitoring frequency would be increased in the case of exceedances of Action/Limit Levels if considered necessary by ET. Monitoring frequency would be maintained as far as practicable.
Sampling Depths & Replication
3.15. During impact water quality monitoring, each station was sampled, and measurements/ water samples were taken at three depths, 1 m below the sea surface, mid-depth, and 1 m above the seabed. For in situ measurements, duplicate readings were made at each water depth at each station. Duplicate water samples were collected at each water depth at each station.
Action and Limit Levels
Pre-operation phase
3.16. The Action and Limit Levels have been set based on the derivation criteria specified in the EM&A Manual. The Action/Limit Levels have been derived and are presented in Table 3.4.
Table 3.4 Derived Action
and Limit Levels
for Water Quality
Parameters |
Action |
Limit |
Pre-operation phase
Impact Monitoring |
||
DO in mg/L |
Surface and Middle 7.30 mg L-1 Bottom 7.31 mg L-1 Tung Lung
Chau Fish Culture Zone 5.1 mgL-1 or level at
control station (Whichever the lower) |
Surface and Middle 4 mg L-1 Bottom 2 mg L-1 Tung Lung
Chau Fish Culture Zone 5.0 mgL-1 or level at control station (Whichever the lower) |
SS in mg/L (Depth-
averaged) |
5.00 mg L-1 or 20% exceedance of value at any impact station
compared with corresponding data from control station |
6.00 mg L-1 or 30% exceedance of value at any
impact station compared with corresponding data from control station |
Turbidity in NTU (Depth- averaged) |