Revision History
Rev. |
Description of Modification |
Date |
1. |
First Issue
for Comments |
15/12/2023 |
2. |
Revised according to comment |
19/12/2023 |
3. |
Revised according to comment |
19/12/2023 |
CONTENTS
7. Summary of Exceedance, Complaints, Notification of Summons and Prosecutions.............. 34
Appendix A Master Programme
Appendix B Overview of Desalination Plant in Tseung Kwan O
Appendix C Summary of Implementation Status of Environmental Mitigation
Appendix D Impact Monitoring Schedule
Appendix E Event/Action Plan
Appendix F Landfill Gas Equipment Calibration Certificate
Appendix G Landfill Gas Monitoring Data
Appendix H Waste Flow Table
Appendix I Site Inspection Proforma
Appendix J Complaint Log
Introduction
A1. The Project, Design, Build and Operate First Stage of Tseung Kwan O Desalination Plant (TKODP), is a Designated Project under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO) and is currently governed by a Further Environmental Permit (EP No. FEP - 01/503/2015/A) for the construction and operation of the Contract.
A2. In accordance with the Environmental Monitoring and Audit (EM&A) Manual for the Contract, EM&A works for marine water quality, noise, waste management and ecology should be carried out by Environmental Team (ET), Acuity Sustainability Consulting Limited (ASCL), during the construction phase of the Contract.
A3. This is the 45th Monthly EM&A Report, prepared by ASCL, for the Contract summarizing the monitoring results and audit findings of the EM&A programme at and around Tseung Kwan O Area 137 (TKO 137) during the reporting period from 1 November to 30 November 2023.
A4. The EM&A programme for this contract has covered environmental monitoring on construction noise level at selected NSRs and Contractor’s environmental performance auditing in the aspects of construction dust, construction noise, water quality, waste management, Landscape and Visual and Ecology.
Summary of Main Works Undertaken & Key Mitigation Measures Implemented
A5. Key activities carried out in this reporting period for the Contract included the followings:
Administration Building -
Carrying out the floor
tiles works at G/F -
Construction of External wall
painting works -
Construction of block wall
in the pipe duct -
Installation of building services, cable laying, electrical switchboard, Pressure Test, testing and commissioning of
electrical switchboard |
Chemical building -
Landscape work at roof -
Repairing the defects inside
the dangerous store -
Defect rectification |
Main Electrical & Central Chiller
Plant Building -
Installation of Roof Tile
for Fuel Tank
Room -
Minor
Installation of building services, electrical switchboard, cable laying,
Pressure Test |
ActiDAFF -
Underground utility construction work |
|
-
Installation of access opening covers for filtered water tank -
Carrying out finishing works
for staircase no. 3 -
Minor
Installation of mechanical equipment, piping system, building services,
electrical switchboards and cable laying, fiber-reinforced plastic cover
Installation |
Product Water
Storage Tank Building -
Installation of Cat Ladders
in Water Tank A -
Sealing slab
opening in water
Tank A -
Re-construction of Wall PW8
in Water Tank A -
Installation of building services, cable laying, Installation of mechanical equipment,
steel pipe, Pressure Test -
Underground utility construction -
Structure Construction |
|
OSCG Building -
Installation of Roller Shutters and Window -
Protective Coating
for dangerous goods
Rooms -
Installation of building services, mechanical equipment and cable -
Placing Soil
Mix at Roof |
|
Reverse Osmosis Building -
Installation of Handrailings -
Installation of Roller Shutters -
Installation of Glass Canopy
and Glass House -
Underground utility construction work -
Installation
of building services, electrical switchboard, cable laying, Minor
Installation of mechanical equipment and steel
pipe and GRP pipe and raised floor, testing and commissioning |
|
Post Treatment Building -
Installation of Cat Ladders
in Water Tanks -
Placing Soil
Mix at Roof -
Forming Opening
at Top of Water Tank for Rescue
Opening -
Installation
of building services, Installation of mechanical equipment and piping system,
Pressure Test |
|
Inspection corridor -
Construction of roof tiling
works -
Installation of steel balustrade at roof -
Installation of Movement Joints -
Installation of glass window -
Installation of building services, Lift Installation |
|
CO2 Tanks -
Installation of pipes and electrical wiring, testing and commissioning Combined Shaft and Pump
room |
|
-
Internal finishing, Grating; window; Louvre
Installation Other -
Glass Roof
and Glass Canopy
installation at elevated walkway -
Security Fence
footing construction work -
Manhole 5 GRP Installation work -
Underground utility
rectification work -
Road Construction -
Footpath Construction -
Landscape Construction -
Irrigation System
Construction -
Water Pressure Test for FS and PL system |
A6. The major environmental impacts brought by the above construction works include:
- Construction dust and noise generation from construction works, excavation works and pipe piling driving works;
- Waste generation from the construction activities; and
A7. The key environmental mitigation measures implemented for the Contract in this reporting period associated with the above construction works include:
- Dust suppression by regular wetting and water spraying for construction works;
- Reduction of noise from equipment and machinery on-site and regular inspection to machinery and plants/vehicles on-site to ensure proper functioning;
- Deployment of silt curtain at the marine areas; and
- Sorting and storage of general refuse and construction waste; and
Summary of exceedance & investigation & follow-up
A8. No noise monitoring was conducted during the reporting period since there are no Contract -related construction activities undertaken within a radius of 300m from the monitoring locations. No exceedance of the action Level was recorded during the reporting period.
A9. The marine water quality programme was ceased from 1 September 2023 due to the completion of marine-related construction works.
A10. Four (4) of dechlorinated effluent sample were taken in contact tank/ product water tank.
A11. No TRC exceedance of action or limit levels was obtained during the discharge of dechlorinated effluent.
A12. In this reporting period, 78 times of landfill gas monitoring were conducted at TKO Area 137 (Ch1+340 - Ch1+600). No action or limit level exceedance was recorded during the reporting period.
A13. Joint site inspections of the construction work by ET and IEC were carried out on 7, 14, 21 and 27 November 2023 to audit the mitigation measures implementation status. Reminders were recorded in the site inspection checklists and provided to the contractors together with the appropriate follow-up actions where necessary.
Complaint Handling and Prosecution
A14. No environmental complaint, notification of summons and prosecution was received in the reporting period.
Reporting Change
A15. There was no change to be reported that may affect the on-going EM&A programme.
Summary of Upcoming
Key Issues and Key Mitigation Measures
A16. Key activities anticipated in the next reporting period for the Contract will include the followings:
Administration Building -
Carrying out the floor
tiles works at G/F -
External wall painting works -
Construction of block work for pipe duct -
Installation
of building services, cable laying, electrical switchboard, testing and
commissioning |
Chemical building -
Installation of leakage collection pit cover -
Underground utility construction work -
Landscape work at roof -
Defect rectification |
Main Electrical & Central Chiller
Plant Building -
Installation of chillers, building services, electrical switchboard and cable laying -
Installation of Roof Tile
for Fuel Tank
Room |
ActiDAFF -
Underground utility construction work -
Installation of access opening cover -
Construction of staircase no 2 -
Installation of mechanical equipment, piping system, installation of building services, electrical switchboards and cable
laying, fiber-reinforced plastic cover Installation |
Product Water
Storage Tank Building -
Installation of Cat Ladders
in Water Tank A -
Sealing slab
opening in water
Tank A -
Re-construction of Wall PW8
in Water Tank A -
Installation
of metal cladding, building services, cable laying, mechanical equipment, steel pipe -
Underground utility construction |
OSCG Building -
Protective Coating
for dangerous goods
Rooms -
Placing Soil
Mix at Roof -
Installation of Metal Cladding (at East Side)
and Roller Shutters and Window -
Underground utility construction work -
Installation of building services, mechanical equipment and cable laying, testing and commissioning |
Reverse Osmosis Building -
Installation
of building services, electrical switchboard, cable laying, Installation of
mechanical equipment, steel pipe, GRP pipe, raised floor, testing and
commissioning -
Installation of metal
cladding, handrailing, roller
shutters, glass canopy and glass house -
Underground utility construction work -
Construction of RC External Wall for Male Toilet |
Post Treatment Building -
Installation
of building services, Installation of mechanical equipment and piping system,
Pressure Test -
Underground utility construction work -
Installation of Cat Ladders
in Water Tanks -
Installation of Metal Cladding -
Placing Soil
Mix at Roof |
Inspection corridor -
Installation of building services, Lift installation -
Construction of roof tiling
works and staircases no. 2 -
Installation of Movement Joints
and glass window |
CO2 Tanks -
Installation of pipes and electrical wiring, testing and commissioning Combined Shaft and Pump
room -
Finishing, Grating; window; louvre installation Other -
Watermain works
at CLP 132
kV Substation -
Staircases construction; Steel Bridge assembly and installation at elevated walkway |
-
Road
Construction, Footpath Construction, Landscape Construction, Irrigation System
Construction, Water Pressure Test for FS and PL system in Zone A, B, C -
Structure
Construction, steel fence erection of Wave Deflector Wall at seawall area |
A17. The major environmental impacts brought by the above construction works will include:
- Construction dust and noise generation from excavation and construction works;
- Waste generation from construction activities
A18. The key environmental mitigation measures for the Contract in the coming reporting period associated with the above construction works will include:
- Reduction of noise from equipment and machinery on-site;
- Dust suppression by regular wetting and water spraying for construction works and at main haul road;
- Sorting and storage of general refuse and construction waste; and
- Deployment of silt curtain at the marine areas.
Background
1.1. The Acciona Agua, S.A. Trading, Jardine Engineering Corporation, Limited and China State Construction Engineering (Hong Kong) Limited as AJC Joint Venture (AJCJV) is contracted to carry out the Design, Build and Operate First Stage of Tseung Kwan O Desalination Plant (DPTKO) under Contract No. 13/WSD/17 (the Contract).
1.2. Acuity Sustainability Consulting Limited (ASCL) is commissioned by AJCJV to undertake the Environmental Team (ET) services as required and/or implied, both explicitly and implicitly, in the Environmental Permit (EP), Environmental Impact Assessment Report (EIA Report) (Register No. AEIAR-192/2015) and Environmental Monitoring and Audit Manual (EM&A Manual) for the Contract; and to carry out the Environmental Monitoring and Audit (EM&A) programme in fulfillment of the EIA Report’s EM&A requirements and Contract No. 13/WSD/17 Specification requirements.
1.3. Pursuant to the Environmental Impact Assessment Ordinance (EIAO), the Director of Environmental Protection granted the Environmental Permit (No. EP-01/503/2015) and Variation of Environmental Permit (No. EP-01/503/2015/A) to Water Supplies Department (WSD); and granted the Further Environmental Permit (No. FEP- 01/503/2015/A) to AJCJV for the Contract.
The Reporting Scope
1.4. This is the 45th Monthly EM&A Report for the Contract which summarizes the key findings of the EM&A programme during the reporting period from 1 November to 30 November 2023.
Contract Organization
1.5. The Contract Organization structure for Construction Phase is presented in Figure 1.1.
Figure 1.1 Contract Organization Chart
1.6. Contact details of the key personnel are presented in Table 1.1 below:
Table 1.1 Contact Details
of Key Personnel
Party |
Position |
Name |
Telephone no. |
Contract Proponent
(Water Supplies Department) |
SE/CM2 |
Milton Law |
2634-3573 |
Supervising Officer (Binnies Hong Kong Limited) |
Project Manager |
Christina Ko |
2608-7302 |
Chief Resident Engineer |
Roger Wu |
6343-1002 |
|
The Jardine Engineering Corporation,
Limited, China State Construction Engineering (Hong Kong) Limited and Acciona Agua, S.A. Trading |
Project Manager |
Stephen Yeung |
2807-4665 |
Environmental Monitoring Manager |
Brian Kam |
9456-9541 |
|
Acuity Sustainability Consulting Limited |
Environmental Team Leader |
Jacky Leung |
2698-6833 |
ANewR
Consulting Limited |
Independent
Environmental Checker (IEC) |
Mr. CHAN Yi Chun, Alex |
2618-2831 |
Summary of Construction Works
1.7. Details of the major construction activities undertaken in this reporting period are shown below. The master programme is presented in Appendix A.
1.8. Key activities carried out in this reporting period for the Contract included the followings:
Administration Building -
Carrying out the floor
tiles works at G/F -
External wall painting works -
Construction of block work for pipe duct -
Installation
of building services, cable laying, electrical switchboard, testing and
commissioning |
Chemical building -
Installation of leakage collection pit cover -
Underground utility construction work -
Landscape work at roof -
Defect rectification |
Main Electrical &
Central Chiller Plant
Building |
-
Installation of chillers, building services, electrical switchboard and cable laying -
Installation of Roof Tile
for Fuel Tank
Room |
ActiDAFF -
Underground utility construction work -
Installation of access opening cover -
Construction of staircase no 2 -
Installation of mechanical equipment, piping system,
installation of building services, electrical
switchboards and cable laying, fiber-reinforced plastic cover Installation |
Product Water
Storage Tank Building -
Installation of Cat Ladders
in Water Tank A -
Sealing slab
opening in water
Tank A -
Re-construction of Wall PW8
in Water Tank
A -
Installation
of metal cladding, building services, cable laying, mechanical equipment, steel pipe -
Underground utility construction |
OSCG Building -
Protective Coating
for dangerous goods
Rooms -
Placing Soil
Mix at Roof -
Installation of Metal Cladding (at East Side) -
Installation of Roller Shutters and Window -
Underground utility construction work -
Installation of building services, mechanical equipment and cable laying, testing and commissioning |
Reverse Osmosis Building -
Installation
of building services, electrical switchboard, cable laying, Installation of
mechanical equipment, steel pipe, GRP pipe, raised floor, testing and
commissioning -
Installation
of metal cladding, handrailing, roller shutters, glass canopy and glass house -
Underground utility construction work -
Construction of RC External Wall for Male Toilet |
Post Treatment Building -
Installation
of building services, Installation of mechanical equipment and piping system,
Pressure Test -
Underground utility construction work -
Installation of Cat Ladders
in Water Tanks
and Metal Cladding -
Placing Soil
Mix at Roof |
Inspection corridor -
Installation of building services, Lift installation |
-
Construction of roof tiling
works and staircases no. 2 -
Installation of Movement Joints
and glass window |
CO2 Tanks -
Installation of pipes and electrical wiring, testing and commissioning Combined Shaft and Pump
room -
Finishing, Grating; window; louvre installation Other -
Watermain works
at CLP 132
kV Substation -
Staircases
construction; Steel Bridge assembly and installation at elevated walkway -
Road
Construction, Footpath Construction, Landscape Construction, Irrigation System
Construction, Water Pressure Test for FS and PL system in Zone A, B, C -
Structure Construction, steel fence erection of Wave Deflector Wall at seawall area |
1.9. A summary of the valid permits, licences, and/or notifications on environmental protection for this Contract is presented in Table 1.2.
Table 1.2 Summary of the Status of Valid Environmental Licence,
Notification, Permit and Documentations
Permit/ Licences |
Valid Period |
Status |
Remark |
|
From |
To |
|||
Environmental Permit |
||||
EP-503/2015/A |
Throughout the Contract |
Valid |
- |
|
FEP - 01/503/2015/A |
Throughout the Contract |
Valid |
- |
|
Notification of Construction Works
under the Air Pollution Control
(Construction Dust) Regulation (Form NA) |
||||
451539 |
Throughout the Contract |
Valid |
- |
|
Billing Account for
Disposal of Construction Waste |
||||
7036276 |
Throughout the Contract |
Valid |
- |
|
Chemical Waste Producer Registration |
||||
5213-839-A2987-01 |
Throughout the Contract |
Valid |
- |
|
Wastewater Discharge Licence (Land
and Marine works) |
||||
WT00035775-2020 |
23/08/2021 |
31/07/2025 |
Valid |
- |
WT00044188-2023 |
16/06/2023 |
30/06/2028 |
Valid |
For
Plant T&C and operation |
Construction Noise Permit |
||||
GW-RE0640-23 |
22/06/2023 |
21/12/2023 |
Valid |
|
1.10. The status for all environmental aspects is presented in Table 1.3.
Table 1.3 Summary of Status for Key Environmental Aspects under the EM&A Manual
Parameters |
Status |
Water Quality |
|
Baseline Monitoring under EM&A Manual |
The baseline water quality monitoring was conducted between 12 May 2020
to 6 Jun 2020. |
Impact Monitoring |
Ceased from
1 September 2023 |
Impact Monitoring of Effluent
Discharge from Main
Disinfection |
On-going |
Noise |
|
Baseline Monitoring |
The baseline
noise monitoring result has been reported in Baseline Monitoring Report and submitted to EPD under
EP Condition 3.4 |
Impact Monitoring |
Completed |
Waste Management |
|
Mitigation Measures in Waste Management Plan |
On-going |
Landfill Gas |
|
Regular Monitoring when construction works are within
the 250 m Consultation Zone |
On-going |
Environmental Audit |
|
Site Inspection covering Measures of Air Quality, Noise
Impact, Water Quality,
Waste, Ecological Quality, Fisheries, Landscape and Visual |
On-going |
1.11. Other than the EM&A work by ET, environmental briefings, trainings, and regular environmental management meetings were conducted, in order to enhance environmental awareness and closely monitor the environmental performance of the contractors.
1.12. The EM&A programme has been implemented in accordance with the recommendations presented in the approved EIA Report and the EM&A Manual. A summary of implementation status of the environmental mitigation measures for the construction phase of the Contract during the reporting period is provided in Appendix C.
Monitoring Requirements
2.1. To ensure no adverse noise impact, noise monitoring is recommended to be carried out within 300m radius from the nearby noise sensitive receivers (NSRs), during construction phase. The NSRs selected as monitoring station are (i) NSR4 - Creative Secondary School, (ii) NSR24 - PLK Laws Foundation College, and (iii) NSR31 - School of Continuing and Professional Studies - CUHK respectively.
2.2. Construction noise level were measured in terms of the A-weighted equivalent continuous sound pressure level (LAeq). Leq 30min was used as the monitoring parameter for the time period between 0700 and 1900 on normal weekdays. Construction works would follow stipulations of the valid Construction Noise Permits if works had to be conducted during restricted hours or public holidays. Table 2.1 summarizes the monitoring parameters, frequency, and duration of the impact noise monitoring.
Table 2.1 Noise Monitoring Parameters, Time, Frequency
and Duration
Time |
Duration |
Interval |
Parameters |
|
Day time: |
Continuously in |
|
Daytime: |
0700-1900 |
Leq 5min/Leq 30min |
Leq 30min |
0700-1900 |
(during normal weekdays) |
(average of 6 consecutive Leq
5min) |
L10 30min & L90
30min |
Monitoring Locations
2.3. The monitoring locations were normally made at a point 1m from the exterior of the NSRs building façade and be at a position 1.2m above the ground. A correction of +3dB(A) should be made to the free-field measurements.
2.4. According to the environmental findings detailed in the EIA report and Baseline Monitoring Report, the designated locations for the construction noise monitoring are listed in Table 2.2 below.
Table 2.2 Noise Sensitive
Receivers
NSR ID |
Noise Sensitive Receivers |
Monitoring Location |
Position |
NSR
4 |
Creative Secondary School |
Roof Floor |
1 m from facade |
NSR
24 |
PLK Laws Foundation College |
Pedestrian Road
on Ground Floor |
Free-field |
NSR
31 |
School of Continuing
and Professional Studies - CUHK |
Roof Floor |
1 m from facade |
2.5. Three noise monitoring locations for impact monitoring at the nearby sensitive receivers are shown in Figure 2.1-2.3.